Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0807 - AVENUE T & SPTCO |
Description: Bridge No. 53C0807 - AVENUE T & SPTCO - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Pearblossom |
Zip Code | 93543 |
Senate District |
17 |
Assembly District | 36 |
Congressional District | 25 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$260 | $-133 | $126 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,234 | $-1,029 | $1,205 | ||||
Local** |
$12 | $0 | $12 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,506 | $-1,163 | $1,343 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$241 | $0 | $241 | $330 | $330 | $-89 | |
Right of Way |
$0 | $0 | $0 | $1 | $1 | $-1 | |
Construction |
$2,265 | $-1,163 | $1,102 | $1,312 | $1,312 | $-210 | |
Total* | $2,506 | $-1,163 | $1,343 | $1,644 | $1,644 | $-300 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
03/09/1990 04/24/2001 |
|
03/09/1990 04/24/2001 |
100 | 03/09/1990 05/23/2001 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/24/2001 10/03/2007 |
|
05/24/2001 10/03/2007 |
100 | 05/24/2001 10/03/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
03/12/2008 05/30/2008 |
10/15/2009 |
03/12/2008 04/24/2008 |
100 | 10/23/2007 04/24/2008 |
5 0 |
Begin Construction Phase
End Construction Phase |
09/30/2008 03/30/2011 |
10/15/2009 10/15/2009 |
09/22/2008 03/30/2011 |
100 | 09/22/2008 01/11/2010 |
0 15 |
Begin Closeout Phase
End Closeout Phase |
07/30/2011 |
|
07/30/2011 |
100 | 01/12/2010 07/12/2011 |
19 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$259,790 |
Current Approved: |
$126,437 |
Actual Expenditures: |
$126,437 |
Status as of December 31, 2023.