Caltrans Logo

Bridge No. 53C0807 - AVENUE T & SPTCO

Description: Bridge No. 53C0807 - AVENUE T & SPTCO - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Pearblossom
Zip Code 93543
 
Senate District
17
Assembly District 36
Congressional District 25
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$260 $-133 $126
Non-bond Funding
State/Federal*
$2,234 $-1,029 $1,205
Local**
$12 $0 $12
Private***
$0 $0 $0
 
Total**** $2,506 $-1,163 $1,343

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$241 $0 $241 $330 $330 $-89
Right of Way
$0 $0 $0 $1 $1 $-1
Construction
$2,265 $-1,163 $1,102 $1,312 $1,312 $-210
 
Total* $2,506 $-1,163 $1,343 $1,644 $1,644 $-300

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
03/09/1990 

04/24/2001 
 

 
03/09/1990 

04/24/2001 
100  03/09/1990 

05/23/2001 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/24/2001 

10/03/2007 
 

 
05/24/2001 

10/03/2007 
100  05/24/2001 

10/03/2007 


Begin Right of Way Phase

End Right of Way Phase
03/12/2008 

05/30/2008 
 

10/15/2009 
03/12/2008 

04/24/2008 
100  10/23/2007 

04/24/2008 


Begin Construction Phase

End Construction Phase
09/30/2008 

03/30/2011 
10/15/2009 

10/15/2009 
09/22/2008 

03/30/2011 
100  09/22/2008 

01/11/2010 


15 
Begin Closeout Phase

End Closeout Phase
07/30/2011 

 
 

 
07/30/2011 

 
100  01/12/2010 

07/12/2011 
19 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$259,790
Current Approved:
$126,437
Actual Expenditures:
$126,437

 

Status as of December 31, 2023.