Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0859 - NORTH SPRING ST & LOS ANGELES RIVER |
Description: Bridge No. 53C0859 - NORTH SPRING ST & LOS ANGELES RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Los Angeles |
Zip Code | 90031 |
Senate District |
22 |
Assembly District | 45 |
Congressional District | 31 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles | Kevin Minne | 213-923-5897 | kevin.minne@lacity.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$229 | $0 | $229 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,771 | $34,278 | $36,048 | ||||
Local** |
$0 | $6,450 | $6,450 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,000 | $40,728 | $42,728 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $6,517 | $6,517 | $6,896 | $6,896 | $-379 | |
Right of Way |
$0 | $6,325 | $6,325 | $3,969 | $6,325 | $0 | |
Construction |
$2,000 | $27,887 | $29,887 | $33,925 | $34,888 | $-5,001 | |
Total* | $2,000 | $40,728 | $42,728 | $44,790 | $48,108 | $-5,380 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
02/13/2003 01/05/2004 |
|
02/13/2003 01/05/2004 |
100 | 02/13/2003 01/05/2004 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/02/2004 08/03/2009 |
10/15/2009 10/15/2009 |
02/02/2004 12/31/2009 |
100 | 02/02/2004 07/31/2012 |
0 -31 |
Begin Right of Way Phase
End Right of Way Phase |
04/03/2008 01/04/2010 |
10/15/2009 10/15/2009 |
04/03/2008 09/30/2010 |
100 | 09/08/2011 03/08/2012 |
-42 -17 |
Begin Construction Phase
End Construction Phase |
09/30/2011 11/01/2013 |
09/16/2013 |
04/10/2012 02/29/2016 |
100 | 04/06/2012 11/19/2018 |
0 -33 |
Begin Closeout Phase
End Closeout Phase |
05/05/2014 |
|
05/05/2014 |
50 | 12/01/2018 07/31/2024 |
-56 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$229,400 |
Current Approved: |
$229,400 |
Actual Expenditures: |
$229,400 |
Status as of December 31, 2023.