Bridge No. 53C0864 - MRTN L KING JR AVE & SPTC RR

Description: Bridge No. 53C0864 - MRTN L KING JR AVE & SPTC RR - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Long Beach
Zip Code 90755, 90806
 
Senate District
27
Assembly District 54
Congressional District 37
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$53 $-1 $51
Non-bond Funding
State/Federal*
$606 $-42 $565
Local**
$13 $0 $13
Private***
$0 $0 $0
 
Total**** $672 $-43 $629

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$211 $-31 $181 $238 $238 $-57
Right of Way
$0 $0 $0 $19 $19 $-19
Construction
$460 $-12 $448 $459 $459 $-11
 
Total* $672 $-43 $629 $715 $715 $-87

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
05/23/1995 

05/12/2002 
 

 
05/23/1995 

05/12/2002 
100  05/23/1995 

05/12/2002 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/12/2002 

03/22/2007 
 

10/15/2009 
06/12/2002 

01/28/2007 
100  06/12/2002 

01/28/2007 


Begin Right of Way Phase

End Right of Way Phase
05/14/2007 

08/09/2007 
 

10/15/2009 
05/14/2007 

09/18/2007 
100  05/09/2007 

09/18/2007 


Begin Construction Phase

End Construction Phase
01/28/2008 

07/30/2009 
10/15/2009 

10/15/2009 
01/03/2008 

08/04/2009 
100  01/03/2008 

08/04/2009 


Begin Closeout Phase

End Closeout Phase
11/30/2009 

 
 

 
11/30/2009 

 
100  08/05/2009 

12/28/2011 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$52,795
Current Approved:
$51,404
Actual Expenditures:
$51,404

 

Status as of December 31, 2023.