Bridge No. 53C0885 - LONG BEACH FWY & ANAHEIM ST |
Description: Bridge No. 53C0885 - LONG BEACH FWY & ANAHEIM ST - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Long Beach |
Zip Code | 90813 |
Senate District |
28 |
Assembly District | 55 |
Congressional District | 46 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$33 | $-4 | $29 | ||||
Non-bond Funding | |||||||
State/Federal* |
$474 | $-61 | $414 | ||||
Local** |
$29 | $0 | $29 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $537 | $-65 | $472 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$247 | $-31 | $216 | $347 | $347 | $-131 | |
Right of Way |
$0 | $0 | $0 | $8 | $8 | $-8 | |
Construction |
$290 | $-34 | $256 | $380 | $380 | $-124 | |
Total* | $537 | $-65 | $472 | $736 | $736 | $-264 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
05/23/1995 10/29/2000 |
|
05/23/1995 10/29/2000 |
100 | 05/23/1995 10/29/2000 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/30/2000 10/03/2007 |
|
10/30/2000 10/03/2007 |
100 | 10/30/2000 10/03/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
08/14/2007 02/11/2008 |
|
08/14/2007 07/07/2008 |
100 | 08/16/2007 07/07/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
06/04/2008 12/30/2009 |
10/15/2009 10/15/2009 |
09/15/2008 10/30/2010 |
100 | 09/15/2008 08/11/2010 |
0 3 |
Begin Closeout Phase
End Closeout Phase |
04/30/2010 |
|
04/30/2010 |
100 | 08/12/2010 06/29/2011 |
-3 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$33,262 |
Current Approved: |
$29,393 |
Actual Expenditures: |
$29,393 |
Status as of December 31, 2023.