Bridge No. 53C0890L - QUEENS WAY-SBND & HARBOR SCENIC DR

Description: Bridge No. 53C0890L - QUEENS WAY-SBND & HARBOR SCENIC DR - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Long Beach
Zip Code 90802
 
Senate District
27
Assembly District 54
Congressional District 46
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Inez Yeung (626) 458-3950   iyeung@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$237 $32 $269
Non-bond Funding
State/Federal*
$2,189 $313 $2,502
Local**
$44 $1,056 $1,100
Private***
$0 $0 $0
 
Total**** $2,470 $1,401 $3,871

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$450 $-109 $341 $341 $341 $0
Right of Way
$0 $15 $15 $15 $15 $0
Construction
$2,020 $1,495 $3,515 $3,515 $3,515 $0
 
Total* $2,470 $1,401 $3,871 $3,871 $3,871 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/21/1995 

04/30/2002 
 

 
04/21/1995 

04/30/2002 
100  04/21/1995 

04/30/2002 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/22/1996 

07/07/2003 
 

 
07/22/1996 

07/07/2003 
100  05/22/2002 

07/07/2003 
-71 

Begin Right of Way Phase

End Right of Way Phase
05/22/2007 

02/11/2008 
 

 
05/22/2007 

07/07/2008 
100  02/02/2007 

07/07/2008 


Begin Construction Phase

End Construction Phase
05/28/2008 

05/30/2011 
10/15/2009 

02/22/2012 
09/09/2008 

11/30/2013 
100  09/09/2008 

11/21/2013 


Begin Closeout Phase

End Closeout Phase
09/30/2011 

 
02/22/2012 

 
12/01/2013 

 
100  11/22/2013 

03/15/2016 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$236,625
Current Approved:
$268,943
Actual Expenditures:
$268,943

 

Status as of December 31, 2023.