Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0892R - QUEENS WAY NBND & SHORELN DR & SEASIDE P |
Description: Bridge No. 53C0892R - QUEENS WAY NBND & SHORELN DR & SEASIDE P - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Long Beach |
Zip Code | 90802 |
Senate District |
27 |
Assembly District | 54 |
Congressional District | 46 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$279 | $0 | $279 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,341 | $99 | $2,440 | ||||
Local** |
$24 | $0 | $24 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,644 | $99 | $2,743 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$339 | $-31 | $308 | $342 | $342 | $-34 | |
Right of Way |
$0 | $0 | $0 | $13 | $13 | $-13 | |
Construction |
$2,305 | $130 | $2,435 | $2,405 | $2,405 | $29 | |
Total* | $2,644 | $99 | $2,743 | $2,761 | $2,761 | $-18 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
05/23/1995 04/17/2001 |
|
05/23/1995 04/17/2001 |
100 | 05/23/1995 05/16/2001 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/17/2001 03/28/2007 |
|
05/17/2001 02/19/2007 |
100 | 05/17/2001 02/19/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
08/17/2006 07/05/2007 |
|
08/17/2006 07/26/2007 |
100 | 08/16/2006 07/26/2007 |
0 0 |
Begin Construction Phase
End Construction Phase |
08/27/2007 08/30/2010 |
10/15/2009 10/15/2009 |
08/27/2007 08/30/2010 |
100 | 08/27/2007 08/09/2010 |
0 1 |
Begin Closeout Phase
End Closeout Phase |
01/30/2011 |
|
01/30/2011 |
100 | 08/10/2010 02/09/2012 |
6 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$279,275 |
Current Approved: |
$279,275 |
Actual Expenditures: |
$273,821 |
Status as of December 31, 2023.