Caltrans Logo

Bridge No. 53C0897 - S.P.T.C. R R & SANTA ANITA AVE UNDER SP

Description: Bridge No. 53C0897 - S.P.T.C. R R & SANTA ANITA AVE UNDER SP - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City El Monte
Zip Code 91731
 
Senate District
24
Assembly District 49
Congressional District 32
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$12 $4 $16
Non-bond Funding
State/Federal*
$320 $32 $352
Local**
$45 $0 $45
Private***
$0 $0 $0
 
Total**** $377 $36 $413

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$273 $0 $273 $305 $305 $-32
Right of Way
$0 $0 $0 $1 $1 $-1
Construction
$104 $36 $139 $169 $169 $-29
 
Total* $377 $36 $413 $476 $476 $-63

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
05/23/1995 

04/30/2001 
 

 
05/23/1995 

04/30/2001 
100  05/23/1995 

05/29/2001 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/30/2001 

02/19/2007 
 

 
05/30/2001 

12/18/2008 
100  05/30/2001 

12/18/2008 


Begin Right of Way Phase

End Right of Way Phase
02/12/2008 

04/26/2008 
 

 
02/12/2008 

03/19/2009 
100  02/01/2009 

03/19/2009 
-12 

Begin Construction Phase

End Construction Phase
09/30/2008 

12/30/2009 
10/15/2009 

10/15/2009 
09/10/2009 

03/31/2011 
100  09/10/2009 

12/30/2010 


Begin Closeout Phase

End Closeout Phase
04/30/2010 

 
 

 
04/01/2011 

 
100  12/31/2010 

08/11/2011 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$11,893
Current Approved:
$15,990
Actual Expenditures:
$15,990

 

Status as of December 31, 2023.