Bridge No. 53C0918 - FIRST ST & TOWNE AVENUE

Description: Bridge No. 53C0918 - FIRST ST & TOWNE AVENUE - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Pomona
Zip Code 91766
 
Senate District
32
Assembly District 61
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$13 $7 $20
Non-bond Funding
State/Federal*
$98 $54 $152
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $111 $61 $171

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $0 $0 $117 $117 $-117
Right of Way
$0 $0 $0 $1 $1 $-1
Construction
$111 $61 $171 $190 $190 $-19
 
Total* $111 $61 $171 $309 $309 $-138

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
08/11/2000 

12/29/2001 
 

 
08/11/2000 

12/29/2001 
100  08/11/2000 

12/29/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/29/2002 

02/11/2007 
 

 
01/29/2002 

02/11/2007 
100  01/29/2002 

02/11/2007 


Begin Right of Way Phase

End Right of Way Phase
06/11/2007 

06/27/2007 
 

10/15/2009 
06/11/2007 

08/23/2007 
100  06/05/2007 

08/23/2007 


Begin Construction Phase

End Construction Phase
10/24/2007 

05/30/2009 
10/15/2009 

10/15/2009 
10/24/2007 

08/04/2009 
100  10/24/2007 

08/04/2009 


Begin Closeout Phase

End Closeout Phase
09/30/2009 

 
 

 
09/30/2009 

 
100  08/05/2009 

08/18/2011 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$12,703
Current Approved:
$19,658
Actual Expenditures:
$19,658

 

Status as of December 31, 2023.