Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0918 - FIRST ST & TOWNE AVENUE |
Description: Bridge No. 53C0918 - FIRST ST & TOWNE AVENUE - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Pomona |
Zip Code | 91766 |
Senate District |
32 |
Assembly District | 61 |
Congressional District | 38 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$13 | $7 | $20 | ||||
Non-bond Funding | |||||||
State/Federal* |
$98 | $54 | $152 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $111 | $61 | $171 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $117 | $117 | $-117 | |
Right of Way |
$0 | $0 | $0 | $1 | $1 | $-1 | |
Construction |
$111 | $61 | $171 | $190 | $190 | $-19 | |
Total* | $111 | $61 | $171 | $309 | $309 | $-138 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
08/11/2000 12/29/2001 |
|
08/11/2000 12/29/2001 |
100 | 08/11/2000 12/29/2001 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/29/2002 02/11/2007 |
|
01/29/2002 02/11/2007 |
100 | 01/29/2002 02/11/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
06/11/2007 06/27/2007 |
10/15/2009 |
06/11/2007 08/23/2007 |
100 | 06/05/2007 08/23/2007 |
0 0 |
Begin Construction Phase
End Construction Phase |
10/24/2007 05/30/2009 |
10/15/2009 10/15/2009 |
10/24/2007 08/04/2009 |
100 | 10/24/2007 08/04/2009 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
09/30/2009 |
|
09/30/2009 |
100 | 08/05/2009 08/18/2011 |
2 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$12,703 |
Current Approved: |
$19,658 |
Actual Expenditures: |
$19,658 |
Status as of December 31, 2023.