Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0930 - 9TH ST & HRBR SCENIC DR/710 FRWY |
Description: Bridge No. 53C0930 - 9TH ST & HRBR SCENIC DR/710 FRWY - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Long Beach |
Zip Code | 90813 |
Senate District |
28 |
Assembly District | 55 |
Congressional District | 46 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Inez Yeung | (626) 458-3950 | iyeung@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$143 | $123 | $266 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,271 | $1,382 | $2,653 | ||||
Local** |
$0 | $1,641 | $1,641 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,414 | $3,146 | $4,560 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$171 | $325 | $496 | $496 | $496 | $0 | |
Right of Way |
$0 | $26 | $26 | $26 | $26 | $0 | |
Construction |
$1,243 | $2,795 | $4,038 | $4,032 | $4,032 | $6 | |
Total* | $1,414 | $3,146 | $4,560 | $4,553 | $4,553 | $6 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
05/23/1995 07/09/2001 |
|
05/23/1995 07/09/2001 |
100 | 05/23/1995 08/08/2001 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/09/2001 03/28/2007 |
10/15/2009 |
08/09/2001 02/20/2007 |
100 | 08/09/2001 02/20/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
08/17/2006 09/17/2007 |
10/15/2009 |
08/17/2006 09/18/2007 |
100 | 08/16/2006 09/18/2007 |
0 0 |
Begin Construction Phase
End Construction Phase |
10/24/2007 10/30/2009 |
10/15/2009 10/15/2009 |
10/24/2007 05/31/2013 |
100 | 10/24/2007 11/07/2013 |
0 -5 |
Begin Closeout Phase
End Closeout Phase |
02/28/2010 |
|
06/01/2013 12/31/2013 |
100 | 11/08/2013 11/07/2016 |
-5 -35 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$142,533 |
Current Approved: |
$259,726 |
Actual Expenditures: |
$259,726 |
Status as of December 31, 2023.