Caltrans Logo

Bridge No. 53C0930 - 9TH ST & HRBR SCENIC DR/710 FRWY

Description: Bridge No. 53C0930 - 9TH ST & HRBR SCENIC DR/710 FRWY - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Long Beach
Zip Code 90813
 
Senate District
28
Assembly District 55
Congressional District 46
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Inez Yeung (626) 458-3950   iyeung@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$143 $123 $266
Non-bond Funding
State/Federal*
$1,271 $1,382 $2,653
Local**
$0 $1,641 $1,641
Private***
$0 $0 $0
 
Total**** $1,414 $3,146 $4,560

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$171 $325 $496 $496 $496 $0
Right of Way
$0 $26 $26 $26 $26 $0
Construction
$1,243 $2,795 $4,038 $4,032 $4,032 $6
 
Total* $1,414 $3,146 $4,560 $4,553 $4,553 $6

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
05/23/1995 

07/09/2001 
 

 
05/23/1995 

07/09/2001 
100  05/23/1995 

08/08/2001 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/09/2001 

03/28/2007 
 

10/15/2009 
08/09/2001 

02/20/2007 
100  08/09/2001 

02/20/2007 


Begin Right of Way Phase

End Right of Way Phase
08/17/2006 

09/17/2007 
 

10/15/2009 
08/17/2006 

09/18/2007 
100  08/16/2006 

09/18/2007 


Begin Construction Phase

End Construction Phase
10/24/2007 

10/30/2009 
10/15/2009 

10/15/2009 
10/24/2007 

05/31/2013 
100  10/24/2007 

11/07/2013 


-5 
Begin Closeout Phase

End Closeout Phase
02/28/2010 

 
 

 
06/01/2013 

12/31/2013 
100  11/08/2013 

11/07/2016 
-5 

-35 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$142,533
Current Approved:
$259,726
Actual Expenditures:
$259,726

 

Status as of December 31, 2023.