Caltrans Logo

Bridge No. 53C0931 - 10TH ST OFF RAMP & 710 FWY/10TH ST. OFFRAMP

Description: Bridge No. 53C0931 - 10TH ST OFF RAMP & 710 FWY/10TH ST. OFFRAMP - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Long Beach
Zip Code 90813
 
Senate District
25
Assembly District 55
Congressional District 46
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$761 $-39 $722
Non-bond Funding
State/Federal*
$6,289 $-301 $5,988
Local**
$64 $0 $64
Private***
$0 $0 $0
 
Total**** $7,114 $-340 $6,774

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$478 $0 $478 $953 $953 $-475
Right of Way
$0 $0 $0 $55 $55 $-55
Construction
$6,636 $-340 $6,296 $6,795 $6,795 $-499
 
Total* $7,114 $-340 $6,774 $7,803 $7,803 $-1,029

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
05/23/1995 

03/14/1997 
 

 
05/23/1995 

03/14/1997 
100  05/23/1995 

04/08/1997 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/09/1997 

09/06/2007 
 

 
04/09/1997 

09/06/2007 
100  04/09/1997 

09/06/2007 


Begin Right of Way Phase

End Right of Way Phase
07/17/2007 

01/15/2008 
 

10/15/2009 
07/17/2007 

07/10/2008 
100  07/03/2007 

07/10/2008 


Begin Construction Phase

End Construction Phase
05/01/2008 

09/30/2011 
10/15/2009 

06/29/2012 
09/22/2008 

03/31/2012 
100  09/22/2008 

03/23/2012 


Begin Closeout Phase

End Closeout Phase
12/30/2011 

 
 

 
03/31/2012 

 
100  03/24/2012 

01/15/2014 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$761,189
Current Approved:
$722,148
Actual Expenditures:
$722,148

 

Status as of December 31, 2023.