Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0931 - 10TH ST OFF RAMP & 710 FWY/10TH ST. OFFRAMP |
Description: Bridge No. 53C0931 - 10TH ST OFF RAMP & 710 FWY/10TH ST. OFFRAMP - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Long Beach |
Zip Code | 90813 |
Senate District |
25 |
Assembly District | 55 |
Congressional District | 46 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$761 | $-39 | $722 | ||||
Non-bond Funding | |||||||
State/Federal* |
$6,289 | $-301 | $5,988 | ||||
Local** |
$64 | $0 | $64 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $7,114 | $-340 | $6,774 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$478 | $0 | $478 | $953 | $953 | $-475 | |
Right of Way |
$0 | $0 | $0 | $55 | $55 | $-55 | |
Construction |
$6,636 | $-340 | $6,296 | $6,795 | $6,795 | $-499 | |
Total* | $7,114 | $-340 | $6,774 | $7,803 | $7,803 | $-1,029 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
05/23/1995 03/14/1997 |
|
05/23/1995 03/14/1997 |
100 | 05/23/1995 04/08/1997 |
0 -1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/09/1997 09/06/2007 |
|
04/09/1997 09/06/2007 |
100 | 04/09/1997 09/06/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
07/17/2007 01/15/2008 |
10/15/2009 |
07/17/2007 07/10/2008 |
100 | 07/03/2007 07/10/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
05/01/2008 09/30/2011 |
10/15/2009 06/29/2012 |
09/22/2008 03/31/2012 |
100 | 09/22/2008 03/23/2012 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
12/30/2011 |
|
03/31/2012 |
100 | 03/24/2012 01/15/2014 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$761,189 |
Current Approved: |
$722,148 |
Actual Expenditures: |
$722,148 |
Status as of December 31, 2023.