Bridge No. 53C0933 - 7TH ST ON RAMP & RTD PARKING LOT UC |
Description: Bridge No. 53C0933 - 7TH ST ON RAMP & RTD PARKING LOT UC - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Long Beach |
Zip Code | 90802 |
Senate District |
25 |
Assembly District | 54 |
Congressional District | 37 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$65 | $14 | $79 | ||||
Non-bond Funding | |||||||
State/Federal* |
$741 | $77 | $818 | ||||
Local** |
$22 | $0 | $22 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $828 | $91 | $919 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$261 | $-31 | $230 | $348 | $348 | $-118 | |
Right of Way |
$0 | $0 | $0 | $23 | $23 | $-23 | |
Construction |
$567 | $122 | $689 | $1,134 | $1,134 | $-445 | |
Total* | $828 | $91 | $919 | $1,505 | $1,505 | $-586 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
05/23/1995 04/12/2003 |
|
05/23/1995 05/11/2003 |
100 | 05/23/1995 05/11/2003 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/12/2003 08/30/2007 |
10/15/2009 |
05/12/2003 02/11/2007 |
100 | 05/12/2003 02/11/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
08/17/2006 09/20/2007 |
10/15/2009 |
08/17/2006 12/12/2007 |
100 | 08/03/2006 12/12/2007 |
0 0 |
Begin Construction Phase
End Construction Phase |
03/11/2008 09/30/2009 |
10/15/2009 10/15/2009 |
02/07/2008 02/29/2012 |
100 | 02/07/2008 10/03/2011 |
0 5 |
Begin Closeout Phase
End Closeout Phase |
01/30/2010 |
|
03/01/2012 09/30/2012 |
100 | 10/04/2011 08/07/2012 |
5 2 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$65,011 |
Current Approved: |
$79,055 |
Actual Expenditures: |
$79,055 |
Status as of December 31, 2023.