Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C0934 - 6TH ST OFF RAMP & GOLDEN AVE & SANFRANCISCO |
Description: Bridge No. 53C0934 - 6TH ST OFF RAMP & GOLDEN AVE & SANFRANCISCO - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Long Beach |
Zip Code | 90802 |
Senate District |
27 |
Assembly District | 54 |
Congressional District | 37 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$441 | $-60 | $381 | ||||
Non-bond Funding | |||||||
State/Federal* |
$3,818 | $-464 | $3,353 | ||||
Local** |
$64 | $0 | $64 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $4,322 | $-525 | $3,798 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$478 | $0 | $478 | $664 | $664 | $-186 | |
Right of Way |
$0 | $0 | $0 | $5 | $5 | $-5 | |
Construction |
$3,844 | $-525 | $3,320 | $3,468 | $3,468 | $-148 | |
Total* | $4,322 | $-525 | $3,798 | $4,136 | $4,136 | $-338 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
05/23/1995 03/14/1997 |
|
05/23/1995 03/14/1997 |
100 | 05/23/1995 03/14/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/09/1997 09/06/2007 |
|
04/09/1997 09/06/2007 |
100 | 04/09/1997 09/06/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
06/28/2007 10/02/2007 |
|
06/28/2007 10/02/2007 |
100 | 06/28/2007 10/02/2007 |
0 0 |
Begin Construction Phase
End Construction Phase |
01/28/2008 05/31/2010 |
10/15/2009 06/29/2012 |
01/03/2008 11/30/2011 |
100 | 01/03/2008 08/16/2011 |
0 4 |
Begin Closeout Phase
End Closeout Phase |
05/30/2011 |
|
09/30/2011 |
100 | 08/17/2011 02/27/2012 |
1 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$440,951 |
Current Approved: |
$380,774 |
Actual Expenditures: |
$380,774 |
Status as of December 31, 2023.