Caltrans Logo

Bridge No. 53C0934 - 6TH ST OFF RAMP & GOLDEN AVE & SANFRANCISCO

Description: Bridge No. 53C0934 - 6TH ST OFF RAMP & GOLDEN AVE & SANFRANCISCO - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Long Beach
Zip Code 90802
 
Senate District
27
Assembly District 54
Congressional District 37
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$441 $-60 $381
Non-bond Funding
State/Federal*
$3,818 $-464 $3,353
Local**
$64 $0 $64
Private***
$0 $0 $0
 
Total**** $4,322 $-525 $3,798

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$478 $0 $478 $664 $664 $-186
Right of Way
$0 $0 $0 $5 $5 $-5
Construction
$3,844 $-525 $3,320 $3,468 $3,468 $-148
 
Total* $4,322 $-525 $3,798 $4,136 $4,136 $-338

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
05/23/1995 

03/14/1997 
 

 
05/23/1995 

03/14/1997 
100  05/23/1995 

03/14/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/09/1997 

09/06/2007 
 

 
04/09/1997 

09/06/2007 
100  04/09/1997 

09/06/2007 


Begin Right of Way Phase

End Right of Way Phase
06/28/2007 

10/02/2007 
 

 
06/28/2007 

10/02/2007 
100  06/28/2007 

10/02/2007 


Begin Construction Phase

End Construction Phase
01/28/2008 

05/31/2010 
10/15/2009 

06/29/2012 
01/03/2008 

11/30/2011 
100  01/03/2008 

08/16/2011 


Begin Closeout Phase

End Closeout Phase
05/30/2011 

 
 

 
09/30/2011 

 
100  08/17/2011 

02/27/2012 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$440,951
Current Approved:
$380,774
Actual Expenditures:
$380,774

 

Status as of December 31, 2023.