Bridge No. 53C1010 - N MAIN ST & LOS ANGELES RIVER

Description: Bridge No. 53C1010 - N MAIN ST & LOS ANGELES RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90031
 
Senate District
22
Assembly District 45
Congressional District 31
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles Shirley Lau (213) 485-5228   Shirley.Lau@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$724 $242 $965
Non-bond Funding
State/Federal*
$1,007 $0 $1,007
Local**
$308 $-135 $173
Private***
$0 $0 $0
 
Total**** $2,038 $106 $2,145

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,179 $0 $1,179 $1,179 $1,179 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$859 $106 $965 $10,955 $11,016 $-10,051
 
Total* $2,038 $106 $2,145 $12,134 $12,195 $-10,051

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
10/04/2001 

10/03/2002 
 

 
10/04/2001 

10/03/2002 
100  10/04/2001 

12/27/2002 


-3 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/05/2004 

01/02/2008 
 

 
04/05/2004 

01/02/2008 
100  04/05/2004 

04/30/2009 


-16 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/02/2008 

06/07/2010 
10/15/2009 

09/26/2012 
10/10/2008 

08/31/2014 
100  10/10/2008 

06/30/2015 


-10 
Begin Closeout Phase

End Closeout Phase
12/01/2010 

 
 

 
12/01/2010 

 
100  07/01/2015 

04/01/2018 
-56 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$723,595
Current Approved:
$965,295
Actual Expenditures:
$965,295

 

Status as of December 31, 2023.