Bridge No. 53C1010 - N MAIN ST & LOS ANGELES RIVER |
Description: Bridge No. 53C1010 - N MAIN ST & LOS ANGELES RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Los Angeles |
Zip Code | 90031 |
Senate District |
22 |
Assembly District | 45 |
Congressional District | 31 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles | Shirley Lau | (213) 485-5228 | Shirley.Lau@lacity.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$724 | $242 | $965 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,007 | $0 | $1,007 | ||||
Local** |
$308 | $-135 | $173 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,038 | $106 | $2,145 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$1,179 | $0 | $1,179 | $1,179 | $1,179 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$859 | $106 | $965 | $10,955 | $11,016 | $-10,051 | |
Total* | $2,038 | $106 | $2,145 | $12,134 | $12,195 | $-10,051 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
10/04/2001 10/03/2002 |
|
10/04/2001 10/03/2002 |
100 | 10/04/2001 12/27/2002 |
0 -3 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/05/2004 01/02/2008 |
|
04/05/2004 01/02/2008 |
100 | 04/05/2004 04/30/2009 |
0 -16 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/02/2008 06/07/2010 |
10/15/2009 09/26/2012 |
10/10/2008 08/31/2014 |
100 | 10/10/2008 06/30/2015 |
0 -10 |
Begin Closeout Phase
End Closeout Phase |
12/01/2010 |
|
12/01/2010 |
100 | 07/01/2015 04/01/2018 |
-56 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$723,595 |
Current Approved: |
$965,295 |
Actual Expenditures: |
$965,295 |
Status as of December 31, 2023.