Caltrans Logo

Bridge No. 53C1184 - 4TH STREET & GRAND AVE

Description: Bridge No. 53C1184 - 4TH STREET & GRAND AVE - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90012
 
Senate District
22
Assembly District 46
Congressional District 34
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles Shirley Lau (213) 485-5228   Shirley.Lau@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$290 $-177 $113
Non-bond Funding
State/Federal*
$2,682 $-1,096 $1,586
Local**
$57 $35 $92
Private***
$0 $0 $0
 
Total**** $3,030 $-1,238 $1,792

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$500 $0 $500 $500 $500 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,530 $-1,238 $1,292 $1,435 $1,435 $-143
 
Total* $3,030 $-1,238 $1,792 $1,935 $1,935 $-143

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
12/17/2004 

02/28/2008 
 

 
12/17/2004 

02/28/2008 
100  12/17/2004 

02/28/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2008 

12/01/2008 
 

 
03/01/2008 

12/01/2008 
100  03/01/2008 

12/01/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2009 

06/06/2011 
10/15/2009 

10/15/2009 
09/21/2009 

05/01/2012 
100  09/21/2009 

12/28/2012 


-8 
Begin Closeout Phase

End Closeout Phase
11/04/2011 

 
 

 
11/04/2011 

 
100  12/31/2012 

12/31/2014 
-14 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$290,191
Current Approved:
$113,195
Actual Expenditures:
$113,195

 

Status as of December 31, 2023.