Bridge No. 53C1184 - 4TH STREET & GRAND AVE |
Description: Bridge No. 53C1184 - 4TH STREET & GRAND AVE - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Los Angeles |
Zip Code | 90012 |
Senate District |
22 |
Assembly District | 46 |
Congressional District | 34 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles | Shirley Lau | (213) 485-5228 | Shirley.Lau@lacity.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$290 | $-177 | $113 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,682 | $-1,096 | $1,586 | ||||
Local** |
$57 | $35 | $92 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $3,030 | $-1,238 | $1,792 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$500 | $0 | $500 | $500 | $500 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$2,530 | $-1,238 | $1,292 | $1,435 | $1,435 | $-143 | |
Total* | $3,030 | $-1,238 | $1,792 | $1,935 | $1,935 | $-143 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
12/17/2004 02/28/2008 |
|
12/17/2004 02/28/2008 |
100 | 12/17/2004 02/28/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/01/2008 12/01/2008 |
|
03/01/2008 12/01/2008 |
100 | 03/01/2008 12/01/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/01/2009 06/06/2011 |
10/15/2009 10/15/2009 |
09/21/2009 05/01/2012 |
100 | 09/21/2009 12/28/2012 |
0 -8 |
Begin Closeout Phase
End Closeout Phase |
11/04/2011 |
|
11/04/2011 |
100 | 12/31/2012 12/31/2014 |
-14 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$290,191 |
Current Approved: |
$113,195 |
Actual Expenditures: |
$113,195 |
Status as of December 31, 2023.