Bridge No. 53C1335 - TAMPA AVE & LOS ANGELES RIVER

Description: Bridge No. 53C1335 - TAMPA AVE & LOS ANGELES RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 91335
 
Senate District
21
Assembly District 40
Congressional District 27
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles Shirley Lau (213) 485-5228   Shirley.Lau@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$60 $0 $60
Non-bond Funding
State/Federal*
$3,919 $19 $3,938
Local**
$459 $70 $529
Private***
$0 $0 $0
 
Total**** $4,438 $89 $4,527

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$115 $699 $814 $1,072 $1,072 $-258
Right of Way
$24 $0 $24 $24 $24 $0
Construction
$4,299 $-610 $3,689 $3,833 $3,833 $-144
 
Total* $4,438 $89 $4,527 $4,929 $4,929 $-402

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
08/27/2002 

01/23/2003 
 

 
08/27/2002 

01/23/2003 
100  08/27/2002 

01/23/2003 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/24/2003 

11/15/2007 
 

 
01/24/2003 

11/15/2007 
100  01/24/2003 

11/15/2007 


Begin Right of Way Phase

End Right of Way Phase
01/05/2007 

06/20/2007 
 

 
01/05/2007 

12/31/2007 
100  01/05/2007 

12/31/2007 


Begin Construction Phase

End Construction Phase
08/10/2007 

08/30/2009 
10/15/2009 

10/15/2009 
07/01/2008 

11/30/2012 
100  07/01/2008 

11/30/2012 


Begin Closeout Phase

End Closeout Phase
12/31/2009 

 
 

 
12/31/2009 

 
100  12/03/2012 

12/31/2014 
-36 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$59,644
Current Approved:
$59,644
Actual Expenditures:
$59,644

 

Status as of December 31, 2023.