Bridge No. 53C1362 - VANOWEN ST & LOS ANGELES RIVER

Description: Bridge No. 53C1362 - VANOWEN ST & LOS ANGELES RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 91306
 
Senate District
20
Assembly District 40
Congressional District 27
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles Shirley Lau (213) 485-5228   Shirley.Lau@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$209 $-209 $0
Non-bond Funding
State/Federal*
$7,178 $-7,178 $0
Local**
$827 $-827 $0
Private***
$0 $0 $0
 
Total**** $8,214 $-8,214 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,100 $-1,100 $0 $0 $0 $0
Right of Way
$34 $-34 $0 $0 $0 $0
Construction
$7,080 $-7,080 $0 $0 $0 $0
 
Total* $8,214 $-8,214 $0 $0 $0 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
08/27/2002 

04/02/2003 
 

 
08/27/2002 

04/02/2003 
100  08/27/2002 

04/02/2003 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/03/2003 

02/28/2008 
 

 
04/03/2003 

02/28/2008 
100  04/03/2003 

02/28/2008 


Begin Right of Way Phase

End Right of Way Phase
05/01/2007 

03/01/2008 
 

 
05/01/2007 

03/01/2008 
100  05/01/2007 

03/01/2008 


Begin Construction Phase

End Construction Phase
07/31/2008 

07/31/2010 
10/15/2009 

10/15/2009 
02/01/2010 

05/01/2012 
98  08/30/2010 

05/16/2014 
-7 

-25 
Begin Closeout Phase

End Closeout Phase
12/31/2010 

 
 

 
12/31/2010 

 
05/16/2014 

08/15/2016 
-41 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.