Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C1362 - VANOWEN ST & LOS ANGELES RIVER |
Description: Bridge No. 53C1362 - VANOWEN ST & LOS ANGELES RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Los Angeles |
Zip Code | 91306 |
Senate District |
20 |
Assembly District | 40 |
Congressional District | 27 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles | Shirley Lau | (213) 485-5228 | Shirley.Lau@lacity.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$209 | $-209 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$7,178 | $-7,178 | $0 | ||||
Local** |
$827 | $-827 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $8,214 | $-8,214 | $0 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$1,100 | $-1,100 | $0 | $0 | $0 | $0 | |
Right of Way |
$34 | $-34 | $0 | $0 | $0 | $0 | |
Construction |
$7,080 | $-7,080 | $0 | $0 | $0 | $0 | |
Total* | $8,214 | $-8,214 | $0 | $0 | $0 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
08/27/2002 04/02/2003 |
|
08/27/2002 04/02/2003 |
100 | 08/27/2002 04/02/2003 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/03/2003 02/28/2008 |
|
04/03/2003 02/28/2008 |
100 | 04/03/2003 02/28/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
05/01/2007 03/01/2008 |
|
05/01/2007 03/01/2008 |
100 | 05/01/2007 03/01/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
07/31/2008 07/31/2010 |
10/15/2009 10/15/2009 |
02/01/2010 05/01/2012 |
98 | 08/30/2010 05/16/2014 |
-7 -25 |
Begin Closeout Phase
End Closeout Phase |
12/31/2010 |
|
12/31/2010 |
0 | 05/16/2014 08/15/2016 |
-41 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.