Bridge No. 53C1388 - WINNETKA AVE & LOS ANGELES RIVER

Description: Bridge No. 53C1388 - WINNETKA AVE & LOS ANGELES RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 91367
 
Senate District
23
Assembly District 40
Congressional District 27
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles Shirley Lau (213) 485-5228   Shirley.Lau@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$45 $0 $45
Non-bond Funding
State/Federal*
$874 $3,521 $4,395
Local**
$120 $465 $585
Private***
$0 $0 $0
 
Total**** $1,039 $3,986 $5,025

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$539 $91 $630 $539 $539 $91
Right of Way
$105 $0 $105 $105 $105 $0
Construction
$395 $3,895 $4,290 $4,527 $4,527 $-237
 
Total* $1,039 $3,986 $5,025 $5,171 $5,171 $-145

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
02/19/2003 

01/10/2005 
 

 
02/19/2003 

01/10/2005 
100  02/19/2003 

01/10/2005 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/11/2005 

12/31/2007 
 

 
01/11/2005 

12/31/2007 
100  01/11/2005 

12/31/2007 


Begin Right of Way Phase

End Right of Way Phase
02/17/2005 

09/19/2007 
 

 
02/17/2005 

09/19/2007 
100  02/17/2005 

09/19/2007 


Begin Construction Phase

End Construction Phase
04/04/2008 

07/30/2010 
10/15/2009 

10/15/2009 
09/11/2008 

11/30/2012 
100  09/11/2008 

11/30/2012 


Begin Closeout Phase

End Closeout Phase
12/31/2010 

 
 

 
12/31/2010 

 
100  12/03/2012 

06/30/2019 
-23 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$45,306
Current Approved:
$45,306
Actual Expenditures:
$45,306

 

Status as of December 31, 2023.