Bridge No. 53C1403 - THE OLD RD & CASTAIC CREEK

Description: Bridge No. 53C1403 - THE OLD RD & CASTAIC CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles County
City Val Verde
Zip Code 91384
 
Senate District
23
Assembly District 40
Congressional District 27
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Masashi Tsujii (626) 458-3950   mtsujii@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$1,050 $-761 $289
Non-bond Funding
State/Federal*
$8,106 $-4,745 $3,361
Local**
$0 $146 $146
Private***
$0 $0 $0
 
Total**** $9,156 $-5,360 $3,797

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $1,277 $1,277 $3,877 $4,330 $-3,054
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$9,156 $-6,636 $2,520 $0 $2,520 $0
 
Total* $9,156 $-5,360 $3,797 $3,877 $6,850 $-3,054

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
03/09/1990 

01/25/1994 
 

 
03/09/1990 

01/25/1994 
100  03/01/1992 

07/31/1992 
-24 

18 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/25/1994 

10/07/2008 
 

 
02/25/1994 

11/03/2022 
91  05/01/2010 

06/03/2024 
-197 

-19 
Begin Right of Way Phase

End Right of Way Phase
01/18/2007 

06/19/2009 
 

 
04/20/2023 

06/01/2023 
75  03/29/2023 

03/31/2024 


-10 
Begin Construction Phase

End Construction Phase
09/30/2009 

12/30/2012 
 

 
10/05/2023 

05/25/2026 
10/31/2024 

07/31/2026 
-13 

-2 
Begin Closeout Phase

End Closeout Phase
04/30/2013 

 
 

 
04/30/2013 

10/30/2026 
08/01/2026 

02/28/2027 
-161 

-4 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.