Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C1403 - THE OLD RD & CASTAIC CREEK |
Description: Bridge No. 53C1403 - THE OLD RD & CASTAIC CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Los Angeles County |
City | Val Verde |
Zip Code | 91384 |
Senate District |
23 |
Assembly District | 40 |
Congressional District | 27 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Masashi Tsujii | (626) 458-3950 | mtsujii@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$1,050 | $-761 | $289 | ||||
Non-bond Funding | |||||||
State/Federal* |
$8,106 | $-4,745 | $3,361 | ||||
Local** |
$0 | $146 | $146 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $9,156 | $-5,360 | $3,797 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $1,277 | $1,277 | $3,877 | $4,330 | $-3,054 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$9,156 | $-6,636 | $2,520 | $0 | $2,520 | $0 | |
Total* | $9,156 | $-5,360 | $3,797 | $3,877 | $6,850 | $-3,054 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
03/09/1990 01/25/1994 |
|
03/09/1990 01/25/1994 |
100 | 03/01/1992 07/31/1992 |
-24 18 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/25/1994 10/07/2008 |
|
02/25/1994 11/03/2022 |
91 | 05/01/2010 06/03/2024 |
-197 -19 |
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 06/19/2009 |
|
04/20/2023 06/01/2023 |
75 | 03/29/2023 03/31/2024 |
1 -10 |
Begin Construction Phase
End Construction Phase |
09/30/2009 12/30/2012 |
|
10/05/2023 05/25/2026 |
0 | 10/31/2024 07/31/2026 |
-13 -2 |
Begin Closeout Phase
End Closeout Phase |
04/30/2013 |
|
04/30/2013 10/30/2026 |
0 | 08/01/2026 02/28/2027 |
-161 -4 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.