Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C1577 - OLEANDER AVE & COMPTON CREEK |
Description: Bridge No. 53C1577 - OLEANDER AVE & COMPTON CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Compton |
Zip Code | 90220 |
Senate District |
25 |
Assembly District | 52 |
Congressional District | 37 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$21 | $-3 | $18 | ||||
Non-bond Funding | |||||||
State/Federal* |
$376 | $-27 | $349 | ||||
Local** |
$12 | $0 | $12 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $409 | $-30 | $379 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$225 | $0 | $225 | $137 | $137 | $89 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $-0 | |
Construction |
$184 | $-30 | $153 | $199 | $199 | $-45 | |
Total* | $409 | $-30 | $379 | $335 | $335 | $43 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
05/23/1995 04/24/2001 |
|
05/23/1995 04/24/2001 |
100 | 05/23/1995 04/24/2001 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/24/2001 01/29/2007 |
|
05/24/2001 01/29/2007 |
100 | 05/24/2001 01/29/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 06/04/2007 |
10/15/2009 |
01/18/2007 06/18/2007 |
100 | 05/29/2007 06/18/2007 |
-4 0 |
Begin Construction Phase
End Construction Phase |
08/21/2007 02/28/2009 |
10/15/2009 10/15/2009 |
08/21/2007 11/05/2008 |
100 | 08/21/2007 11/05/2008 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/30/2009 |
|
06/30/2009 |
100 | 11/06/2008 10/24/2011 |
8 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$21,066 |
Current Approved: |
$17,584 |
Actual Expenditures: |
$17,584 |
Status as of December 31, 2023.