Bridge No. 53C1829 - OAK GROVE DR & ARROYO SECO |
Description: Bridge No. 53C1829 - OAK GROVE DR & ARROYO SECO - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Pasadena |
Zip Code | 91001 |
Senate District |
21 |
Assembly District | 44 |
Congressional District | 26, 29 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$286 | $-42 | $244 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,390 | $-327 | $2,063 | ||||
Local** |
$16 | $0 | $16 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,692 | $-369 | $2,323 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$199 | $0 | $199 | $371 | $371 | $-172 | |
Right of Way |
$0 | $0 | $0 | $1 | $1 | $-1 | |
Construction |
$2,493 | $-369 | $2,124 | $2,135 | $2,135 | $-11 | |
Total* | $2,692 | $-369 | $2,323 | $2,507 | $2,507 | $-184 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
07/13/1995 08/12/1999 |
|
07/13/1995 08/12/1999 |
100 | 07/13/1995 08/12/1999 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/12/1999 03/26/2007 |
10/15/2009 |
09/12/1999 12/19/2007 |
100 | 09/12/1999 02/19/2007 |
0 10 |
Begin Right of Way Phase
End Right of Way Phase |
01/18/2007 05/31/2007 |
10/15/2009 |
01/18/2007 06/11/2007 |
100 | 05/16/2007 06/11/2007 |
-3 0 |
Begin Construction Phase
End Construction Phase |
07/31/2007 04/30/2010 |
10/15/2009 10/15/2009 |
07/31/2007 04/30/2010 |
100 | 07/31/2007 11/03/2009 |
0 6 |
Begin Closeout Phase
End Closeout Phase |
08/30/2010 |
|
08/30/2010 |
100 | 11/04/2009 11/28/2011 |
10 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$285,915 |
Current Approved: |
$243,580 |
Actual Expenditures: |
$242,594 |
Status as of December 31, 2023.