Caltrans Logo

Bridge No. 53C1851 - OAK GROVE DRIVE & FLINT CANYON WASH

Description: Bridge No. 53C1851 - OAK GROVE DRIVE & FLINT CANYON WASH - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City La Canada Flintridge, Pasadena
Zip Code 91001
 
Senate District
21
Assembly District 44
Congressional District 26, 29
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$254 $-11 $243
Non-bond Funding
State/Federal*
$2,272 $-16 $2,257
Local**
$55 $0 $55
Private***
$0 $0 $0
 
Total**** $2,581 $-27 $2,555

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$464 $-30 $434 $500 $500 $-66
Right of Way
$0 $0 $0 $1 $1 $-1
Construction
$2,118 $3 $2,121 $2,144 $2,144 $-23
 
Total* $2,581 $-27 $2,555 $2,645 $2,645 $-90

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
07/13/1995 

10/23/1999 
 

 
07/13/1995 

10/23/1999 
100  07/13/1995 

10/23/1999 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/23/1999 

04/03/2007 
 

10/15/2009 
11/23/1999 

02/19/2007 
100  11/29/1999 

02/19/2007 


Begin Right of Way Phase

End Right of Way Phase
01/18/2007 

06/25/2007 
 

10/15/2009 
01/18/2007 

06/28/2007 
100  05/16/2007 

06/28/2007 
-3 

Begin Construction Phase

End Construction Phase
10/22/2007 

04/30/2010 
10/15/2009 

10/15/2009 
10/22/2007 

04/30/2010 
100  10/22/2007 

11/03/2009 


Begin Closeout Phase

End Closeout Phase
08/30/2010 

 
 

 
08/30/2010 

 
100  11/04/2009 

12/20/2011 
10 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$254,457
Current Approved:
$243,263
Actual Expenditures:
$243,263

 

Status as of December 31, 2023.