Bridge No. 53C1875 - AVENUE 26 & ARROYO SECO CHANNEL

Description: Bridge No. 53C1875 - AVENUE 26 & ARROYO SECO CHANNEL - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90031
 
Senate District
22
Assembly District 45
Congressional District 31
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles Shirley Lau (213) 485-5228   Shirley.Lau@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$229 $-40 $189
Non-bond Funding
State/Federal*
$5,313 $-3,202 $2,111
Local**
$557 $-60 $497
Private***
$0 $0 $0
 
Total**** $6,099 $-3,303 $2,797

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,017 $-224 $793 $845 $1,017 $-224
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5,083 $-3,079 $2,004 $1,007 $5,263 $-3,259
 
Total* $6,099 $-3,303 $2,797 $1,853 $6,280 $-3,483

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
11/28/2000 

11/25/2002 
 

 
11/28/2000 

11/25/2002 
100  11/28/2000 

11/25/2002 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/25/2002 

07/30/2010 
10/15/2009 

10/15/2009 
11/25/2002 

01/31/2012 
100  11/25/2002 

06/30/2014 


-29 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  06/25/2014 

03/30/2015 


Begin Construction Phase

End Construction Phase
01/04/2010 

05/03/2012 
10/15/2009 

10/15/2009 
10/04/2012 

02/03/2014 
100  08/01/2014 

06/30/2015 
-22 

-17 
Begin Closeout Phase

End Closeout Phase
11/04/2012 

 
 

 
11/04/2012 

 
50  07/01/2015 

06/30/2018 
-32 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$229,400
Current Approved:
$189,298
Actual Expenditures:
$115,543

 

Status as of December 31, 2023.