Bridge No. 53C1880 - SIXTH ST & LOS ANGELES RIVER

Description: Bridge No. 53C1880 - SIXTH ST & LOS ANGELES RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90021
 
Senate District
22
Assembly District 46
Congressional District 34
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles Kevin Minne 213-923-5897   kevin.minne@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$25,807 $6,045 $31,852
Non-bond Funding
State/Federal*
$215,189 $181,126 $396,315
Local**
$4,000 $2,298 $6,298
Private***
$0 $0 $0
 
Total**** $244,996 $189,469 $434,465

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$20,000 $22,166 $42,166 $42,126 $42,126 $40
Right of Way
$52,000 $62,604 $114,604 $129,166 $135,062 $-20,458
Construction
$172,996 $104,699 $277,695 $415,668 $418,999 $-141,304
 
Total* $244,996 $189,469 $434,465 $586,960 $596,187 $-161,723

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/30/2000 

06/30/2004 
 

 
01/30/2000 

06/30/2004 
100  01/30/2000 

06/30/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/06/2006 

07/02/2010 
10/15/2009 

10/15/2009 
10/06/2006 

12/02/2010 
100  07/01/2011 

03/20/2019 
-58 

-101 
Begin Right of Way Phase

End Right of Way Phase
05/03/2010 

08/05/2011 
10/15/2009 

10/15/2009 
05/03/2010 

03/04/2013 
100  04/06/2012 

12/10/2015 
-23 

-34 
Begin Construction Phase

End Construction Phase
05/02/2011 

09/15/2014 
10/15/2009 

10/15/2009 
04/01/2013 

12/30/2016 
100  01/05/2015 

07/10/2022 
-21 

-67 
Begin Closeout Phase

End Closeout Phase
09/15/2015 

 
 

 
09/15/2015 

 
25  07/10/2022 

12/31/2024 
-83 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.