Bridge No. 53C1881 - HYPERION AVE & GLENDALE BL SB, LA RIV

Description: Bridge No. 53C1881 - HYPERION AVE & GLENDALE BL SB, LA RIV - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles County
City Los Angeles
Zip Code 90039
 
Senate District
21
Assembly District 45
Congressional District 31
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles Kevin Minne 213-923-5897   kevin.minne@lacity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$418 $1,690 $2,108
Non-bond Funding
State/Federal*
$12,013 $9,405 $21,417
Local**
$1,307 $0 $1,307
Private***
$0 $0 $0
 
Total**** $13,738 $11,094 $24,832

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,755 $2,505 $4,260 $4,883 $5,020 $-760
Right of Way
$1,150 $222 $1,372 $980 $1,000 $372
Construction
$10,833 $8,367 $19,200 $0 $33,327 $-14,127
 
Total* $13,738 $11,094 $24,832 $5,863 $39,347 $-14,515

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
11/28/2000 

06/30/2004 
 

 
11/28/2000 

06/30/2004 
100  11/28/2000 

06/30/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2004 

10/09/2009 
 

 
06/30/2004 

09/01/2021 
100  06/30/2004 

09/13/2022 


-13 
Begin Right of Way Phase

End Right of Way Phase
09/02/2009 

03/31/2010 
 

 
05/15/2015 

09/01/2021 
100  05/15/2015 

08/29/2022 


-12 
Begin Construction Phase

End Construction Phase
04/01/2010 

01/02/2013 
 

 
09/30/2021 

06/30/2027 
05/01/2024 

07/16/2028 
-31 

-13 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

06/30/2028 
07/17/2028 

07/17/2030 


-25 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.