Caltrans Logo

Bridge No. 53C1915 - 4TH ST & ALHAMBRA HIGH SCHOOL POC

Description: Bridge No. 53C1915 - 4TH ST & ALHAMBRA HIGH SCHOOL POC - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles County
City Alhambra
Zip Code 91801
 
Senate District
22
Assembly District 49
Congressional District 29
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Los Angeles County Allan Abramson (626) 458-3950   aabrams@dpw.lacounty.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$48 $-11 $38
Non-bond Funding
State/Federal*
$508 $-82 $426
Local**
$11 $0 $11
Private***
$0 $0 $0
 
Total**** $567 $-93 $474

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$147 $0 $147 $263 $263 $-116
Right of Way
$0 $0 $0 $5 $5 $-5
Construction
$420 $-93 $327 $351 $351 $-24
 
Total* $567 $-93 $474 $619 $619 $-145

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
05/23/1995 

11/10/1998 
 

 
05/23/1995 

11/10/1998 
100  05/23/1995 

11/10/1998 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/10/1998 

01/30/2008 
 

 
12/10/1998 

01/30/2008 
100  12/10/1998 

11/14/2007 


Begin Right of Way Phase

End Right of Way Phase
08/16/2007 

05/01/2008 
 

 
08/16/2007 

05/01/2008 
100  11/07/2007 

01/28/2008 
-3 

Begin Construction Phase

End Construction Phase
08/19/2008 

02/28/2010 
 

 
08/19/2008 

02/28/2010 
100  06/23/2008 

10/06/2009 


Begin Closeout Phase

End Closeout Phase
06/30/2010 

 
 

 
06/30/2010 

 
100  12/09/2010 

 
-5 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$48,176
Current Approved:
$37,502
Actual Expenditures:
$37,502

 

Status as of December 31, 2023.