Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 53C1915 - 4TH ST & ALHAMBRA HIGH SCHOOL POC |
Description: Bridge No. 53C1915 - 4TH ST & ALHAMBRA HIGH SCHOOL POC - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles County |
City | Alhambra |
Zip Code | 91801 |
Senate District |
22 |
Assembly District | 49 |
Congressional District | 29 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Los Angeles County | Allan Abramson | (626) 458-3950 | aabrams@dpw.lacounty.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$48 | $-11 | $38 | ||||
Non-bond Funding | |||||||
State/Federal* |
$508 | $-82 | $426 | ||||
Local** |
$11 | $0 | $11 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $567 | $-93 | $474 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$147 | $0 | $147 | $263 | $263 | $-116 | |
Right of Way |
$0 | $0 | $0 | $5 | $5 | $-5 | |
Construction |
$420 | $-93 | $327 | $351 | $351 | $-24 | |
Total* | $567 | $-93 | $474 | $619 | $619 | $-145 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
05/23/1995 11/10/1998 |
|
05/23/1995 11/10/1998 |
100 | 05/23/1995 11/10/1998 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/10/1998 01/30/2008 |
|
12/10/1998 01/30/2008 |
100 | 12/10/1998 11/14/2007 |
0 3 |
Begin Right of Way Phase
End Right of Way Phase |
08/16/2007 05/01/2008 |
|
08/16/2007 05/01/2008 |
100 | 11/07/2007 01/28/2008 |
-3 3 |
Begin Construction Phase
End Construction Phase |
08/19/2008 02/28/2010 |
|
08/19/2008 02/28/2010 |
100 | 06/23/2008 10/06/2009 |
2 5 |
Begin Closeout Phase
End Closeout Phase |
06/30/2010 |
|
06/30/2010 |
100 | 12/09/2010 |
-5 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$48,176 |
Current Approved: |
$37,502 |
Actual Expenditures: |
$37,502 |
Status as of December 31, 2023.