Bridge No. 54C0066 - MT VERNON AVE & BNSF RY,AMTRAK,UP RR,3RD

Description: Bridge No. 54C0066 - MT VERNON AVE & BNSF RY,AMTRAK,UP RR,3RD - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Bernardino County
City San Bernardino
Zip Code 92418
 
Senate District
32
Assembly District 62
Congressional District 43
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
SBCTA Tim Hilton (909) 884-8276   thilton@gosbcta.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$3,453 $0 $3,453
Non-bond Funding
State/Federal*
$36,756 $115,628 $152,383
Local**
$447 $15,843 $16,290
Private***
$0 $0 $0
 
Total**** $40,656 $131,471 $172,126

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$3,252 $10,518 $13,770 $21,492 $22,680 $-8,910
Right of Way
$725 $65,572 $66,297 $68,950 $72,211 $-5,914
Construction
$36,678 $55,381 $92,059 $53,870 $149,920 $-57,861
 
Total* $40,656 $131,471 $172,126 $144,313 $244,811 $-72,685

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/22/1997 

02/28/2009 
10/15/2009 

10/15/2009 
04/22/1997 

07/30/2010 
100  11/30/2010 

06/29/2011 
-165 

-11 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/28/2009 

11/30/2009 
 

 
06/01/2020 

07/31/2022 
100  09/30/2012 

10/04/2019 
93 

34 
Begin Right of Way Phase

End Right of Way Phase
02/28/2009 

11/30/2009 
 

 
05/31/2019 

07/31/2022 
100  05/09/2018 

10/04/2019 
13 

34 
Begin Construction Phase

End Construction Phase
01/30/2010 

08/30/2011 
 

 
07/31/2020 

07/31/2024 
51  06/05/2020 

09/30/2025 


-14 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

06/30/2025 
10/01/2025 

10/31/2026 


-16 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.