Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 54C0066 - MT VERNON AVE & BNSF RY,AMTRAK,UP RR,3RD |
Description: Bridge No. 54C0066 - MT VERNON AVE & BNSF RY,AMTRAK,UP RR,3RD - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Bernardino County |
City | San Bernardino |
Zip Code | 92418 |
Senate District |
32 |
Assembly District | 62 |
Congressional District | 43 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
SBCTA | Tim Hilton | (909) 884-8276 | thilton@gosbcta.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$3,453 | $0 | $3,453 | ||||
Non-bond Funding | |||||||
State/Federal* |
$36,756 | $115,628 | $152,383 | ||||
Local** |
$447 | $15,843 | $16,290 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $40,656 | $131,471 | $172,126 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$3,252 | $10,518 | $13,770 | $21,492 | $22,680 | $-8,910 | |
Right of Way |
$725 | $65,572 | $66,297 | $68,950 | $72,211 | $-5,914 | |
Construction |
$36,678 | $55,381 | $92,059 | $53,870 | $149,920 | $-57,861 | |
Total* | $40,656 | $131,471 | $172,126 | $144,313 | $244,811 | $-72,685 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/22/1997 02/28/2009 |
10/15/2009 10/15/2009 |
04/22/1997 07/30/2010 |
100 | 11/30/2010 06/29/2011 |
-165 -11 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/28/2009 11/30/2009 |
|
06/01/2020 07/31/2022 |
100 | 09/30/2012 10/04/2019 |
93 34 |
Begin Right of Way Phase
End Right of Way Phase |
02/28/2009 11/30/2009 |
|
05/31/2019 07/31/2022 |
100 | 05/09/2018 10/04/2019 |
13 34 |
Begin Construction Phase
End Construction Phase |
01/30/2010 08/30/2011 |
|
07/31/2020 07/31/2024 |
51 | 06/05/2020 09/30/2025 |
2 -14 |
Begin Closeout Phase
End Closeout Phase |
|
|
06/30/2025 |
0 | 10/01/2025 10/31/2026 |
0 -16 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.