Bridge No. 54C0077 - LA CADENA DR & SANTA ANA RIVER |
Description: Bridge No. 54C0077 - LA CADENA DR & SANTA ANA RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Bernardino County |
City | Colton |
Zip Code | 92324 |
Senate District |
32 |
Assembly District | 62 |
Congressional District | 43 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Colton | Victor Ortiz | (909) 370-5065 | VOrtiz@coltonca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$134 | $0 | $134 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,504 | $22,873 | $24,377 | ||||
Local** |
$117 | $2,907 | $3,024 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,755 | $25,780 | $27,535 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$585 | $2,190 | $2,775 | $2,363 | $2,363 | $412 | |
Right of Way |
$0 | $1,159 | $1,159 | $291 | $850 | $309 | |
Construction |
$1,170 | $22,431 | $23,601 | $325 | $21,353 | $2,248 | |
Total* | $1,755 | $25,780 | $27,535 | $2,979 | $24,566 | $2,969 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
02/20/1996 02/20/1997 |
|
02/20/1996 02/20/1997 |
100 | 02/20/1996 02/20/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 07/01/2009 |
|
01/01/2009 06/30/2019 |
100 | 01/01/2009 06/30/2019 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
07/01/2019 12/31/2020 |
95 | 09/01/2018 06/30/2024 |
10 -43 |
Begin Construction Phase
End Construction Phase |
08/30/2009 07/31/2010 |
|
01/15/2021 06/30/2023 |
0 | 07/01/2024 06/30/2026 |
-42 -37 |
Begin Closeout Phase
End Closeout Phase |
|
|
12/31/2023 |
0 | 07/01/2026 12/31/2026 |
0 -37 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.