Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 54C0078 - LA CADENA DRIVE & BNSF RY,AMTRAK,METROLINK |
Description: Bridge No. 54C0078 - LA CADENA DRIVE & BNSF RY,AMTRAK,METROLINK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino County |
City | Colton |
Zip Code | 92324 |
Senate District |
32 |
Assembly District | 62 |
Congressional District | 43 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Colton | Victor Ortiz | (909)370-5065 | vortiz@ci.colton.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$15 | $0 | $15 | ||||
Non-bond Funding | |||||||
State/Federal* |
$155 | $0 | $155 | ||||
Local** |
$5 | $0 | $5 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $175 | $0 | $175 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$45 | $0 | $45 | $84 | $96 | $-51 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$130 | $0 | $130 | $195 | $205 | $-75 | |
Total* | $175 | $0 | $175 | $279 | $301 | $-126 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
02/20/1996 02/20/1997 |
|
02/20/1996 02/20/1997 |
100 | 02/20/1996 02/20/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 07/01/2009 |
10/15/2009 |
01/01/2009 12/31/2010 |
100 | 01/01/2009 03/31/2014 |
0 -40 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | 07/01/2014 08/28/2014 |
0 0 |
Begin Construction Phase
End Construction Phase |
08/30/2009 07/31/2010 |
10/15/2009 10/15/2009 |
01/01/2011 08/31/2011 |
100 | 10/01/2014 09/30/2016 |
-46 -62 |
Begin Closeout Phase
End Closeout Phase |
06/30/2010 |
10/15/2009 |
09/01/2011 12/31/2012 |
100 | 10/01/2016 07/31/2019 |
-62 -80 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$14,911 |
Current Approved: |
$14,911 |
Actual Expenditures: |
$11,928 |
Status as of December 31, 2023.