Bridge No. 54C0078 - LA CADENA DRIVE & BNSF RY,AMTRAK,METROLINK

Description: Bridge No. 54C0078 - LA CADENA DRIVE & BNSF RY,AMTRAK,METROLINK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino County
City Colton
Zip Code 92324
 
Senate District
32
Assembly District 62
Congressional District 43
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Colton Victor Ortiz (909)370-5065   vortiz@ci.colton.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$15 $0 $15
Non-bond Funding
State/Federal*
$155 $0 $155
Local**
$5 $0 $5
Private***
$0 $0 $0
 
Total**** $175 $0 $175

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$45 $0 $45 $84 $96 $-51
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$130 $0 $130 $195 $205 $-75
 
Total* $175 $0 $175 $279 $301 $-126

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
02/20/1996 

02/20/1997 
 

 
02/20/1996 

02/20/1997 
100  02/20/1996 

02/20/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

07/01/2009 
 

10/15/2009 
01/01/2009 

12/31/2010 
100  01/01/2009 

03/31/2014 


-40 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  07/01/2014 

08/28/2014 


Begin Construction Phase

End Construction Phase
08/30/2009 

07/31/2010 
10/15/2009 

10/15/2009 
01/01/2011 

08/31/2011 
100  10/01/2014 

09/30/2016 
-46 

-62 
Begin Closeout Phase

End Closeout Phase
06/30/2010 

 
10/15/2009 

 
09/01/2011 

12/31/2012 
100  10/01/2016 

07/31/2019 
-62 

-80 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$14,911
Current Approved:
$14,911
Actual Expenditures:
$11,928

 

Status as of December 31, 2023.