Bridge No. 54C0088 - N 1ST AVENUE & BNSF RY, UP RR, AMTRAK

Description: Bridge No. 54C0088 - N 1ST AVENUE & BNSF RY, UP RR, AMTRAK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Bernardino County
City Barstow
Zip Code 92311
 
Senate District
18
Assembly District 34
Congressional District 25
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Barstow Fidel Martinez (760) 255-5156   fmartinez@barstowca.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$298 $7 $305
Non-bond Funding
State/Federal*
$2,302 $14,444 $16,745
Local**
$0 $2,170 $2,170
Private***
$0 $0 $0
 
Total**** $2,600 $16,620 $19,220

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $7,425 $7,425 $5,281 $8,277 $-852
Right of Way
$0 $11,490 $11,490 $2,550 $16,720 $-5,231
Construction
$2,600 $-2,295 $305 $0 $67,892 $-67,587
 
Total* $2,600 $16,620 $19,220 $7,831 $92,890 $-73,670

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

04/28/1998 
 

 
 

04/28/1998 
100  06/01/2015 

12/01/2016 


-226 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/04/2008 

02/04/2010 
 

 
02/04/2008 

04/30/2021 
100  05/01/2017 

05/06/2019 
-112 

24 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
10/31/2016 

12/31/2020 
80  05/01/2017 

11/30/2024 
-6 

-48 
Begin Construction Phase

End Construction Phase
09/30/2011 

03/30/2013 
 

 
02/28/2022 

03/30/2024 
25  01/26/2023 

05/16/2025 
-11 

-14 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

03/30/2025 
05/17/2025 

05/15/2026 


-14 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.