Bridge No. 54C0089 - N 1ST AVENUE & MOJAVE RIVER |
Description: Bridge No. 54C0089 - N 1ST AVENUE & MOJAVE RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Bernardino County |
City | Barstow |
Zip Code | 92311 |
Senate District |
18 |
Assembly District | 34 |
Congressional District | 25 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Barstow | Fidel Martinez | (760) 255-5156 | fmartinez@barstowca.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$82 | $0 | $82 | ||||
Non-bond Funding | |||||||
State/Federal* |
$633 | $4,625 | $5,258 | ||||
Local** |
$0 | $700 | $700 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $715 | $5,324 | $6,039 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $5,139 | $5,139 | $2,061 | $1,695 | $3,444 | |
Right of Way |
$0 | $818 | $818 | $0 | $0 | $818 | |
Construction |
$715 | $-633 | $82 | $0 | $715 | $-633 | |
Total* | $715 | $5,324 | $6,039 | $2,061 | $2,410 | $3,629 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/28/1998 09/08/1999 |
|
04/28/1998 09/01/1999 |
100 | 12/07/2015 02/06/2023 |
-214 -285 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/04/2008 02/04/2010 |
|
08/31/2014 02/28/2023 |
90 | 02/07/2023 02/06/2026 |
-103 -36 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
01/31/2021 02/28/2023 |
2 | 02/07/2023 02/06/2026 |
-25 -36 |
Begin Construction Phase
End Construction Phase |
09/30/2011 03/30/2013 |
|
06/30/2023 10/31/2025 |
0 | 12/01/2026 03/08/2028 |
-42 -29 |
Begin Closeout Phase
End Closeout Phase |
|
|
10/31/2026 |
0 | 03/08/2028 03/06/2029 |
0 -29 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.