Bridge No. 54C0100 - MT VERNON AVE & SANTA ANA RIVER |
Description: Bridge No. 54C0100 - MT VERNON AVE & SANTA ANA RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Bernardino County |
City | Colton |
Zip Code | 92324 |
Senate District |
32 |
Assembly District | 62 |
Congressional District | 43 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Colton | Victor Ortiz | (909) 370-5065 | VOrtiz@coltonca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$71 | $346 | $418 | ||||
Non-bond Funding | |||||||
State/Federal* |
$799 | $2,950 | $3,748 | ||||
Local** |
$62 | $6 | $68 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $932 | $3,302 | $4,234 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$311 | $283 | $594 | $142 | $908 | $-314 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$621 | $3,019 | $3,640 | $0 | $4,452 | $-812 | |
Total* | $932 | $3,302 | $4,234 | $142 | $5,360 | $-1,126 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/29/1992 01/29/1993 |
|
01/29/1992 01/29/1993 |
85 | 01/29/1992 03/31/2024 |
0 -379 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 07/01/2009 |
10/29/2021 10/29/2021 |
07/01/2020 06/30/2023 |
10 | 01/01/2009 12/31/2024 |
140 -18 |
Begin Right of Way Phase
End Right of Way Phase |
|
10/29/2021 10/29/2021 |
06/01/2022 06/30/2023 |
0 | 01/01/2025 12/31/2025 |
-31 -30 |
Begin Construction Phase
End Construction Phase |
08/30/2009 07/31/2010 |
10/29/2021 10/29/2021 |
07/01/2023 12/31/2024 |
0 | 01/01/2026 06/30/2027 |
-30 -30 |
Begin Closeout Phase
End Closeout Phase |
|
10/29/2021 10/29/2021 |
06/30/2025 |
0 | 07/01/2027 12/31/2027 |
0 -30 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.