Bridge No. 54C0100 - MT VERNON AVE & SANTA ANA RIVER

Description: Bridge No. 54C0100 - MT VERNON AVE & SANTA ANA RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Bernardino County
City Colton
Zip Code 92324
 
Senate District
32
Assembly District 62
Congressional District 43
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Colton Victor Ortiz (909) 370-5065   VOrtiz@coltonca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$71 $346 $418
Non-bond Funding
State/Federal*
$799 $2,950 $3,748
Local**
$62 $6 $68
Private***
$0 $0 $0
 
Total**** $932 $3,302 $4,234

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$311 $283 $594 $142 $908 $-314
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$621 $3,019 $3,640 $0 $4,452 $-812
 
Total* $932 $3,302 $4,234 $142 $5,360 $-1,126

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/29/1992 

01/29/1993 
 

 
01/29/1992 

01/29/1993 
85  01/29/1992 

03/31/2024 


-379 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

07/01/2009 
10/29/2021 

10/29/2021 
07/01/2020 

06/30/2023 
10  01/01/2009 

12/31/2024 
140 

-18 
Begin Right of Way Phase

End Right of Way Phase
 

 
10/29/2021 

10/29/2021 
06/01/2022 

06/30/2023 
01/01/2025 

12/31/2025 
-31 

-30 
Begin Construction Phase

End Construction Phase
08/30/2009 

07/31/2010 
10/29/2021 

10/29/2021 
07/01/2023 

12/31/2024 
01/01/2026 

06/30/2027 
-30 

-30 
Begin Closeout Phase

End Closeout Phase
 

 
10/29/2021 

10/29/2021 
 

06/30/2025 
07/01/2027 

12/31/2027 


-30 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.