Bridge No. 54C0130 - ANDERSON ST & UP RR & AMTRAK |
Description: Bridge No. 54C0130 - ANDERSON ST & UP RR & AMTRAK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino County |
City | Loma Linda |
Zip Code | 92354 |
Senate District |
31 |
Assembly District | 63 |
Congressional District | 41 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Loma Linda | Jarb Thaipejr | (909) 799-2811 | jthaipejr@lomalinda-ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$26 | $0 | $26 | ||||
Non-bond Funding | |||||||
State/Federal* |
$212 | $0 | $212 | ||||
Local** |
$20 | $0 | $20 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $259 | $0 | $259 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$29 | $0 | $29 | $20 | $20 | $9 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$230 | $0 | $230 | $218 | $218 | $12 | |
Total* | $259 | $0 | $259 | $238 | $238 | $20 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/22/1996 04/22/1997 |
|
04/22/1996 04/22/1997 |
100 | 04/22/1996 04/22/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2008 12/31/2009 |
|
01/01/2008 12/31/2009 |
100 | 01/01/2008 12/31/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | 10/01/2008 05/01/2009 |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2010 09/30/2011 |
|
09/30/2010 09/30/2011 |
100 | 10/31/2011 01/24/2012 |
-13 -4 |
Begin Closeout Phase
End Closeout Phase |
04/30/2012 |
|
04/30/2012 |
50 | 04/30/2012 08/27/2013 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$26,381 |
Current Approved: |
$26,381 |
Actual Expenditures: |
$25,052 |
Status as of December 31, 2023.