Caltrans Logo

Bridge No. 54C0130 - ANDERSON ST & UP RR & AMTRAK

Description: Bridge No. 54C0130 - ANDERSON ST & UP RR & AMTRAK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino County
City Loma Linda
Zip Code 92354
 
Senate District
31
Assembly District 63
Congressional District 41
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Loma Linda Jarb Thaipejr (909) 799-2811   jthaipejr@lomalinda-ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$26 $0 $26
Non-bond Funding
State/Federal*
$212 $0 $212
Local**
$20 $0 $20
Private***
$0 $0 $0
 
Total**** $259 $0 $259

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$29 $0 $29 $20 $20 $9
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$230 $0 $230 $218 $218 $12
 
Total* $259 $0 $259 $238 $238 $20

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/22/1996 

04/22/1997 
 

 
04/22/1996 

04/22/1997 
100  04/22/1996 

04/22/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2008 

12/31/2009 
 

 
01/01/2008 

12/31/2009 
100  01/01/2008 

12/31/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  10/01/2008 

05/01/2009 


Begin Construction Phase

End Construction Phase
09/30/2010 

09/30/2011 
 

 
09/30/2010 

09/30/2011 
100  10/31/2011 

01/24/2012 
-13 

-4 
Begin Closeout Phase

End Closeout Phase
04/30/2012 

 
 

 
04/30/2012 

 
50  04/30/2012 

08/27/2013 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$26,381
Current Approved:
$26,381
Actual Expenditures:
$25,052

 

Status as of December 31, 2023.