Bridge No. 54C0379 - BARTON RD & UP RR |
Description: Bridge No. 54C0379 - BARTON RD & UP RR - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Bernardino County |
City | |
Zip Code | 92313 |
Senate District |
31 |
Assembly District | 63 |
Congressional District | 41 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Colton | Victor Ortiz | (909) 370-5065 | VOrtiz@coltonca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$52 | $-1 | $52 | ||||
Non-bond Funding | |||||||
State/Federal* |
$857 | $2,216 | $3,073 | ||||
Local** |
$350 | $-3 | $347 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,259 | $2,212 | $3,471 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$700 | $95 | $795 | $634 | $795 | $0 | |
Right of Way |
$104 | $496 | $600 | $79 | $600 | $0 | |
Construction |
$455 | $1,621 | $2,076 | $0 | $455 | $1,621 | |
Total* | $1,259 | $2,212 | $3,471 | $714 | $1,850 | $1,621 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
03/19/1997 |
|
03/19/1997 |
100 | 03/01/1997 06/01/1997 |
0 -2 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/1999 09/01/2009 |
|
06/30/2019 12/31/2021 |
100 | 07/01/2019 06/30/2022 |
0 -6 |
Begin Right of Way Phase
End Right of Way Phase |
12/01/2007 06/01/2008 |
|
07/31/2021 06/30/2022 |
35 | 03/01/2022 12/31/2024 |
-7 -30 |
Begin Construction Phase
End Construction Phase |
10/01/2009 08/01/2010 |
|
07/31/2022 12/31/2023 |
0 | 01/01/2025 12/31/2025 |
-29 -24 |
Begin Closeout Phase
End Closeout Phase |
|
|
05/31/2024 |
0 | 01/01/2026 06/30/2026 |
0 -25 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.