Bridge No. 54C0379 - BARTON RD & UP RR

Description: Bridge No. 54C0379 - BARTON RD & UP RR - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Bernardino County
City
Zip Code 92313
 
Senate District
31
Assembly District 63
Congressional District 41
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Colton Victor Ortiz (909) 370-5065   VOrtiz@coltonca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$52 $-1 $52
Non-bond Funding
State/Federal*
$857 $2,216 $3,073
Local**
$350 $-3 $347
Private***
$0 $0 $0
 
Total**** $1,259 $2,212 $3,471

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$700 $95 $795 $634 $795 $0
Right of Way
$104 $496 $600 $79 $600 $0
Construction
$455 $1,621 $2,076 $0 $455 $1,621
 
Total* $1,259 $2,212 $3,471 $714 $1,850 $1,621

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

03/19/1997 
 

 
 

03/19/1997 
100  03/01/1997 

06/01/1997 


-2 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/1999 

09/01/2009 
 

 
06/30/2019 

12/31/2021 
100  07/01/2019 

06/30/2022 


-6 
Begin Right of Way Phase

End Right of Way Phase
12/01/2007 

06/01/2008 
 

 
07/31/2021 

06/30/2022 
35  03/01/2022 

12/31/2024 
-7 

-30 
Begin Construction Phase

End Construction Phase
10/01/2009 

08/01/2010 
 

 
07/31/2022 

12/31/2023 
01/01/2025 

12/31/2025 
-29 

-24 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

05/31/2024 
01/01/2026 

06/30/2026 


-25 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.