Bridge No. 54C0496 - DUNCAN RD & CALIFORNIA AQUEDUCT |
Description: Bridge No. 54C0496 - DUNCAN RD & CALIFORNIA AQUEDUCT - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino County |
City | Victorville |
Zip Code | 92392 |
Senate District |
17 |
Assembly District | 36 |
Congressional District | 25 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Department of Water Resources | Ray Miller | (916) 653-9443 | rhmiller@water.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$17 | $1 | $18 | ||||
Non-bond Funding | |||||||
State/Federal* |
$212 | $88 | $300 | ||||
Local** |
$10 | $0 | $10 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $240 | $89 | $329 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$90 | $0 | $90 | $97 | $97 | $-7 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$150 | $89 | $239 | $202 | $202 | $36 | |
Total* | $240 | $89 | $329 | $300 | $300 | $29 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
08/26/2005 02/16/2007 |
|
08/26/2005 02/16/2007 |
100 | 10/01/2005 11/01/2007 |
-1 -9 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/16/2007 12/18/2007 |
10/15/2009 |
04/16/2007 09/30/2010 |
100 | 10/01/2010 03/01/2013 |
-42 -29 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2008 04/01/2009 |
10/15/2009 10/15/2009 |
10/01/2010 06/30/2011 |
100 | 05/01/2014 04/08/2015 |
-44 -46 |
Begin Closeout Phase
End Closeout Phase |
10/01/2009 |
10/15/2009 |
09/30/2011 |
100 | 04/08/2015 11/06/2020 |
-43 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$17,205 |
Current Approved: |
$18,272 |
Actual Expenditures: |
$13,645 |
Status as of December 31, 2023.