Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 54C0583 - YUCCA ST & BNSF RY, AMTRAK, & UP RR |
Description: Bridge No. 54C0583 - YUCCA ST & BNSF RY, AMTRAK, & UP RR - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino County |
City | Barstow |
Zip Code | 92311 |
Senate District |
18 |
Assembly District | 34 |
Congressional District | 25 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Barstow | Domingo Gonzales, Asst. Engr. | (760) 255-5156 | dgonzales@barstowca.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$19 | $-19 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$150 | $-150 | $0 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $169 | $-169 | $0 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $97 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$169 | $-169 | $0 | $0 | $550 | $-550 | |
Total* | $169 | $-169 | $0 | $97 | $550 | $-550 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
03/19/1997 |
|
03/19/1997 |
50 | 01/02/2018 01/04/2021 |
0 -290 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/04/2008 02/04/2008 |
10/15/2009 10/15/2009 |
02/04/2008 12/31/2010 |
0 | 01/04/2021 07/02/2021 |
-157 -128 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
04/10/2010 10/11/2010 |
0 | 01/04/2021 07/05/2021 |
-131 -131 |
Begin Construction Phase
End Construction Phase |
09/30/2011 03/30/2013 |
10/15/2009 10/15/2009 |
09/30/2011 03/30/2013 |
0 | 07/05/2021 07/04/2022 |
-119 -113 |
Begin Closeout Phase
End Closeout Phase |
09/30/2013 |
10/15/2009 |
09/30/2013 |
0 | 07/05/2022 07/03/2023 |
-107 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.