Bridge No. 54C0583 - YUCCA ST & BNSF RY, AMTRAK, & UP RR

Description: Bridge No. 54C0583 - YUCCA ST & BNSF RY, AMTRAK, & UP RR - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino County
City Barstow
Zip Code 92311
 
Senate District
18
Assembly District 34
Congressional District 25
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Barstow Domingo Gonzales, Asst. Engr. (760) 255-5156   dgonzales@barstowca.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$19 $-19 $0
Non-bond Funding
State/Federal*
$150 $-150 $0
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $169 $-169 $0

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $0 $0 $97 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$169 $-169 $0 $0 $550 $-550
 
Total* $169 $-169 $0 $97 $550 $-550

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

03/19/1997 
 

 
 

03/19/1997 
50  01/02/2018 

01/04/2021 


-290 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/04/2008 

02/04/2008 
10/15/2009 

10/15/2009 
02/04/2008 

12/31/2010 
01/04/2021 

07/02/2021 
-157 

-128 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
04/10/2010 

10/11/2010 
01/04/2021 

07/05/2021 
-131 

-131 
Begin Construction Phase

End Construction Phase
09/30/2011 

03/30/2013 
10/15/2009 

10/15/2009 
09/30/2011 

03/30/2013 
07/05/2021 

07/04/2022 
-119 

-113 
Begin Closeout Phase

End Closeout Phase
09/30/2013 

 
10/15/2009 

 
09/30/2013 

 
07/05/2022 

07/03/2023 
-107 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.