Bridge No. 55C0015 - PARK AVENUE & GRAND CANAL

Description: Bridge No. 55C0015 - PARK AVENUE & GRAND CANAL - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange County
City Newport Beach
Zip Code 92660
 
Senate District
35
Assembly District 70
Congressional District 48
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Newport Beach FONG TSE 949-644-3321   FTSE@newportbeachca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$146 $-146 $0
Non-bond Funding
State/Federal*
$1,129 $0 $1,129
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $1,275 $-146 $1,129

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $0 $0 $886 $886 $-886
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,275 $-146 $1,129 $1,285 $8,370 $-7,241
 
Total* $1,275 $-146 $1,129 $2,171 $9,256 $-8,127

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
10/18/2001 

06/18/2003 
 

 
10/18/2001 

06/18/2003 
100  10/18/2001 

06/18/2003 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2009 

10/01/2010 
 

10/15/2009 
06/01/2009 

12/15/2011 
100  06/05/2012 

03/31/2016 
-37 

-52 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

10/15/2009 
02/19/2011 

03/07/2012 
100  05/19/2014 

09/30/2015 
-39 

-43 
Begin Construction Phase

End Construction Phase
09/30/2011 

03/03/2012 
10/15/2009 

10/15/2009 
03/12/2012 

11/15/2012 
15  04/04/2016 

03/31/2017 
-49 

-53 
Begin Closeout Phase

End Closeout Phase
09/03/2012 

 
10/15/2009 

 
12/28/2013 

 
04/01/2017 

09/30/2017 
-40 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.