Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 55C0015 - PARK AVENUE & GRAND CANAL |
Description: Bridge No. 55C0015 - PARK AVENUE & GRAND CANAL - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange County |
City | Newport Beach |
Zip Code | 92660 |
Senate District |
35 |
Assembly District | 70 |
Congressional District | 48 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Newport Beach | FONG TSE | 949-644-3321 | FTSE@newportbeachca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$146 | $-146 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,129 | $0 | $1,129 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,275 | $-146 | $1,129 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $886 | $886 | $-886 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,275 | $-146 | $1,129 | $1,285 | $8,370 | $-7,241 | |
Total* | $1,275 | $-146 | $1,129 | $2,171 | $9,256 | $-8,127 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
10/18/2001 06/18/2003 |
|
10/18/2001 06/18/2003 |
100 | 10/18/2001 06/18/2003 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2009 10/01/2010 |
10/15/2009 |
06/01/2009 12/15/2011 |
100 | 06/05/2012 03/31/2016 |
-37 -52 |
Begin Right of Way Phase
End Right of Way Phase |
|
10/15/2009 |
02/19/2011 03/07/2012 |
100 | 05/19/2014 09/30/2015 |
-39 -43 |
Begin Construction Phase
End Construction Phase |
09/30/2011 03/03/2012 |
10/15/2009 10/15/2009 |
03/12/2012 11/15/2012 |
15 | 04/04/2016 03/31/2017 |
-49 -53 |
Begin Closeout Phase
End Closeout Phase |
09/03/2012 |
10/15/2009 |
12/28/2013 |
0 | 04/01/2017 09/30/2017 |
-40 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.