Bridge No. 55C0038 - SANTIAGO CNYN ROAD & SANTIAGO CREEK |
Description: Bridge No. 55C0038 - SANTIAGO CNYN ROAD & SANTIAGO CREEK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange County |
City | Silverado |
Zip Code | 92676 |
Senate District |
33 |
Assembly District | 71 |
Congressional District | 48 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Orange County | Harry Persaud | (714) 834-2694 | harry.persaud@rdmd.ocgov.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$55 | $0 | $55 | ||||
Non-bond Funding | |||||||
State/Federal* |
$427 | $80 | $507 | ||||
Local** |
$0 | $0 | $0 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $483 | $80 | $563 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$483 | $80 | $563 | $1,880 | $1,880 | $-1,317 | |
Total* | $483 | $80 | $563 | $1,880 | $1,880 | $-1,317 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
10/18/2002 06/03/2003 |
|
10/18/2002 06/03/2003 |
100 | 10/18/2002 06/03/2003 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/03/2003 01/11/2007 |
10/15/2009 |
06/03/2003 05/21/2007 |
100 | 06/03/2003 05/21/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/15/2008 12/30/2010 |
10/15/2009 10/15/2009 |
04/16/2008 05/20/2009 |
100 | 04/16/2008 05/20/2009 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
12/30/2011 |
|
12/30/2011 |
100 | 09/30/2011 09/24/2012 |
3 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$55,379 |
Current Approved: |
$65,727 |
Actual Expenditures: |
$63,477 |
Status as of December 31, 2023.