Caltrans Logo

Bridge No. 55C0038 - SANTIAGO CNYN ROAD & SANTIAGO CREEK

Description: Bridge No. 55C0038 - SANTIAGO CNYN ROAD & SANTIAGO CREEK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange County
City Silverado
Zip Code 92676
 
Senate District
33
Assembly District 71
Congressional District 48
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Orange County Harry Persaud (714) 834-2694   harry.persaud@rdmd.ocgov.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$55 $0 $55
Non-bond Funding
State/Federal*
$427 $80 $507
Local**
$0 $0 $0
Private***
$0 $0 $0
 
Total**** $483 $80 $563

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$483 $80 $563 $1,880 $1,880 $-1,317
 
Total* $483 $80 $563 $1,880 $1,880 $-1,317

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
10/18/2002 

06/03/2003 
 

 
10/18/2002 

06/03/2003 
100  10/18/2002 

06/03/2003 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/03/2003 

01/11/2007 
 

10/15/2009 
06/03/2003 

05/21/2007 
100  06/03/2003 

05/21/2007 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/15/2008 

12/30/2010 
10/15/2009 

10/15/2009 
04/16/2008 

05/20/2009 
100  04/16/2008 

05/20/2009 


Begin Closeout Phase

End Closeout Phase
12/30/2011 

 
 

 
12/30/2011 

 
100  09/30/2011 

09/24/2012 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$55,379
Current Approved:
$65,727
Actual Expenditures:
$63,477

 

Status as of December 31, 2023.