Bridge No. 55C0656 - RTE 55 DEPARTURES & RTE 55 ARRIVALS RAMP |
Description: Bridge No. 55C0656 - RTE 55 DEPARTURES & RTE 55 ARRIVALS RAMP - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Orange County |
City | Santa Ana |
Zip Code | 92707 |
Senate District |
35 |
Assembly District | 70 |
Congressional District | 46 |
Caltrans District |
12 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Orange County | Larry Serafini | (949) 252-5270 | lserafini@ocair.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$110 | $0 | $110 | ||||
Non-bond Funding | |||||||
State/Federal* |
$945 | $0 | $945 | ||||
Local** |
$25 | $0 | $25 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,080 | $0 | $1,080 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$125 | $0 | $125 | $125 | $125 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$955 | $0 | $955 | $955 | $955 | $0 | |
Total* | $1,080 | $0 | $1,080 | $1,080 | $1,080 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
09/30/2002 02/01/2007 |
|
09/30/2002 02/01/2007 |
100 | 09/30/2002 02/01/2007 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/30/2007 01/30/2008 |
10/15/2009 |
08/30/2007 10/01/2009 |
100 | 08/30/2007 10/01/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
11/01/2009 05/06/2011 |
10/15/2009 10/15/2009 |
01/01/2010 10/31/2011 |
100 | 09/20/2010 01/09/2014 |
-9 -27 |
Begin Closeout Phase
End Closeout Phase |
10/30/2011 |
|
10/30/2011 |
100 | 01/09/2014 12/04/2015 |
-27 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$109,536 |
Current Approved: |
$683,555 |
Actual Expenditures: |
$683,555 |
Status as of December 31, 2023.