Caltrans Logo

Bridge No. 56C0001L - S/B VAN BUREN BLVD & SANTA ANA RIVER

Description: Bridge No. 56C0001L - S/B VAN BUREN BLVD & SANTA ANA RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside County
City
Zip Code 92504
 
Senate District
31
Assembly District 66
Congressional District 44
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Riverside County Khalid Nasim, Engineering Div. Mgr. (951) 955-3337   KNasim@rivco.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$1,952 $-636 $1,317
Non-bond Funding
State/Federal*
$17,774 $-6,371 $11,403
Local**
$198 $0 $198
Private***
$0 $0 $0
 
Total**** $19,924 $-7,007 $12,917

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,438 $0 $1,438 $1,279 $1,279 $158
Right of Way
$49 $-49 $0 $0 $0 $0
Construction
$18,437 $-6,957 $11,480 $16,574 $16,574 $-5,094
 
Total* $19,924 $-7,007 $12,917 $17,853 $17,853 $-4,936

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
11/20/1996 

04/09/1997 
 

 
11/20/1996 

04/09/1997 
100  11/20/1996 

04/09/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/10/2001 

03/15/2008 
 

 
04/10/2001 

06/03/2008 
100  04/18/2000 

06/03/2008 
12 

Begin Right of Way Phase

End Right of Way Phase
01/25/2008 

08/30/2008 
 

 
01/25/2008 

06/04/2008 
100  04/02/2008 

07/23/2008 
-2 

-2 
Begin Construction Phase

End Construction Phase
09/30/2008 

03/31/2011 
10/15/2009 

 
03/22/2009 

01/31/2014 
100  09/22/2008 

09/22/2013 


Begin Closeout Phase

End Closeout Phase
09/15/2011 

 
 

 
03/25/2014 

 
100  03/25/2014 

06/30/2023 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$1,952,339
Current Approved:
$1,316,701
Actual Expenditures:
$1,316,701

 

Status as of December 31, 2023.