Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 56C0001L - S/B VAN BUREN BLVD & SANTA ANA RIVER |
Description: Bridge No. 56C0001L - S/B VAN BUREN BLVD & SANTA ANA RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside County |
City | |
Zip Code | 92504 |
Senate District |
31 |
Assembly District | 66 |
Congressional District | 44 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Riverside County | Khalid Nasim, Engineering Div. Mgr. | (951) 955-3337 | KNasim@rivco.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$1,952 | $-636 | $1,317 | ||||
Non-bond Funding | |||||||
State/Federal* |
$17,774 | $-6,371 | $11,403 | ||||
Local** |
$198 | $0 | $198 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $19,924 | $-7,007 | $12,917 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$1,438 | $0 | $1,438 | $1,279 | $1,279 | $158 | |
Right of Way |
$49 | $-49 | $0 | $0 | $0 | $0 | |
Construction |
$18,437 | $-6,957 | $11,480 | $16,574 | $16,574 | $-5,094 | |
Total* | $19,924 | $-7,007 | $12,917 | $17,853 | $17,853 | $-4,936 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
11/20/1996 04/09/1997 |
|
11/20/1996 04/09/1997 |
100 | 11/20/1996 04/09/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/10/2001 03/15/2008 |
|
04/10/2001 06/03/2008 |
100 | 04/18/2000 06/03/2008 |
12 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/25/2008 08/30/2008 |
|
01/25/2008 06/04/2008 |
100 | 04/02/2008 07/23/2008 |
-2 -2 |
Begin Construction Phase
End Construction Phase |
09/30/2008 03/31/2011 |
10/15/2009 |
03/22/2009 01/31/2014 |
100 | 09/22/2008 09/22/2013 |
6 4 |
Begin Closeout Phase
End Closeout Phase |
09/15/2011 |
|
03/25/2014 |
100 | 03/25/2014 06/30/2023 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$1,952,339 |
Current Approved: |
$1,316,701 |
Actual Expenditures: |
$1,316,701 |
Status as of December 31, 2023.