Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 56C0017 - RIVER ROAD & SANTA ANA RIVER |
Description: Bridge No. 56C0017 - RIVER ROAD & SANTA ANA RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside County |
City | |
Zip Code | 92860 |
Senate District |
37 |
Assembly District | 71 |
Congressional District | 44 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Riverside County | Tayfun Saglam, Proj. Mgr. | (951)955-2871 | tsaglam@rctlma.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$1,290 | $-1,269 | $22 | ||||
Non-bond Funding | |||||||
State/Federal* |
$59,370 | $-19,188 | $40,182 | ||||
Local** |
$6,793 | $-1,188 | $5,605 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $67,453 | $-21,644 | $45,809 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$4,360 | $61 | $4,421 | $4,642 | $4,642 | $-222 | |
Right of Way |
$815 | $-31 | $784 | $452 | $452 | $332 | |
Construction |
$62,278 | $-21,674 | $40,604 | $43,020 | $43,020 | $-2,416 | |
Total* | $67,453 | $-21,644 | $45,809 | $48,114 | $48,114 | $-2,306 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
02/27/2007 04/15/2008 |
|
02/27/2007 04/15/2008 |
100 | 07/16/2008 08/15/2009 |
-16 -16 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/24/1998 11/16/2007 |
|
02/24/1998 04/24/2008 |
100 | 07/22/1996 04/24/2008 |
19 0 |
Begin Right of Way Phase
End Right of Way Phase |
08/18/2007 04/30/2008 |
|
08/18/2007 03/20/2008 |
100 | 08/18/2007 03/20/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
09/30/2008 03/31/2011 |
10/15/2009 10/15/2009 |
04/24/2008 12/15/2010 |
100 | 04/24/2008 05/23/2011 |
0 -5 |
Begin Closeout Phase
End Closeout Phase |
09/30/2011 |
|
09/30/2011 |
50 | 11/05/2013 12/31/2014 |
-26 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$1,290,375 |
Current Approved: |
$21,678 |
Actual Expenditures: |
$21,678 |
Status as of December 31, 2023.