Caltrans Logo

Bridge No. 56C0017 - RIVER ROAD & SANTA ANA RIVER

Description: Bridge No. 56C0017 - RIVER ROAD & SANTA ANA RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside County
City
Zip Code 92860
 
Senate District
37
Assembly District 71
Congressional District 44
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Riverside County Tayfun Saglam, Proj. Mgr. (951)955-2871   tsaglam@rctlma.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$1,290 $-1,269 $22
Non-bond Funding
State/Federal*
$59,370 $-19,188 $40,182
Local**
$6,793 $-1,188 $5,605
Private***
$0 $0 $0
 
Total**** $67,453 $-21,644 $45,809

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$4,360 $61 $4,421 $4,642 $4,642 $-222
Right of Way
$815 $-31 $784 $452 $452 $332
Construction
$62,278 $-21,674 $40,604 $43,020 $43,020 $-2,416
 
Total* $67,453 $-21,644 $45,809 $48,114 $48,114 $-2,306

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
02/27/2007 

04/15/2008 
 

 
02/27/2007 

04/15/2008 
100  07/16/2008 

08/15/2009 
-16 

-16 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/24/1998 

11/16/2007 
 

 
02/24/1998 

04/24/2008 
100  07/22/1996 

04/24/2008 
19 

Begin Right of Way Phase

End Right of Way Phase
08/18/2007 

04/30/2008 
 

 
08/18/2007 

03/20/2008 
100  08/18/2007 

03/20/2008 


Begin Construction Phase

End Construction Phase
09/30/2008 

03/31/2011 
10/15/2009 

10/15/2009 
04/24/2008 

12/15/2010 
100  04/24/2008 

05/23/2011 


-5 
Begin Closeout Phase

End Closeout Phase
09/30/2011 

 
 

 
09/30/2011 

 
50  11/05/2013 

12/31/2014 
-26 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$1,290,375
Current Approved:
$21,678
Actual Expenditures:
$21,678

 

Status as of December 31, 2023.