Bridge No. 56C0071 - MSSN BL/BUENA VST & SANTA ANA RIVER

Description: Bridge No. 56C0071 - MSSN BL/BUENA VST & SANTA ANA RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Riverside County
City
Zip Code 92509
 
Senate District
31
Assembly District 66
Congressional District 44
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Riverside County Cesar Tolentino, Proj. Mgr. (951) 955-1520   ctolenti@rivco.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$3,728 $-1,044 $2,684
Non-bond Funding
State/Federal*
$28,772 $21,033 $49,805
Local**
$454 $3,315 $3,769
Private***
$0 $0 $0
 
Total**** $32,954 $23,304 $56,258

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$454 $5,665 $6,119 $7,627 $9,000 $-2,881
Right of Way
$500 $700 $1,200 $175 $1,200 $0
Construction
$32,000 $16,939 $48,939 $0 $69,476 $-20,537
 
Total* $32,954 $23,304 $56,258 $7,801 $79,676 $-23,418

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
11/21/1996 

04/09/1997 
 

 
11/21/1996 

04/09/1997 
100  11/21/1996 

07/01/2019 


-271 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/15/2008 

04/30/2014 
 

 
07/08/2010 

08/30/2022 
98  07/01/2019 

04/01/2024 
-109 

-19 
Begin Right of Way Phase

End Right of Way Phase
05/01/2013 

04/30/2014 
 

 
09/01/2019 

07/30/2022 
50  09/01/2019 

05/31/2024 


-22 
Begin Construction Phase

End Construction Phase
01/15/2015 

07/15/2017 
 

 
09/06/2022 

12/30/2024 
06/01/2024 

06/30/2027 
-21 

-30 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

08/30/2025 
07/01/2027 

12/31/2027 


-28 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.