Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 56C0071 - MSSN BL/BUENA VST & SANTA ANA RIVER |
Description: Bridge No. 56C0071 - MSSN BL/BUENA VST & SANTA ANA RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Riverside County |
City | |
Zip Code | 92509 |
Senate District |
31 |
Assembly District | 66 |
Congressional District | 44 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Riverside County | Cesar Tolentino, Proj. Mgr. | (951) 955-1520 | ctolenti@rivco.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$3,728 | $-1,044 | $2,684 | ||||
Non-bond Funding | |||||||
State/Federal* |
$28,772 | $21,033 | $49,805 | ||||
Local** |
$454 | $3,315 | $3,769 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $32,954 | $23,304 | $56,258 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$454 | $5,665 | $6,119 | $7,627 | $9,000 | $-2,881 | |
Right of Way |
$500 | $700 | $1,200 | $175 | $1,200 | $0 | |
Construction |
$32,000 | $16,939 | $48,939 | $0 | $69,476 | $-20,537 | |
Total* | $32,954 | $23,304 | $56,258 | $7,801 | $79,676 | $-23,418 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
11/21/1996 04/09/1997 |
|
11/21/1996 04/09/1997 |
100 | 11/21/1996 07/01/2019 |
0 -271 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/15/2008 04/30/2014 |
|
07/08/2010 08/30/2022 |
98 | 07/01/2019 04/01/2024 |
-109 -19 |
Begin Right of Way Phase
End Right of Way Phase |
05/01/2013 04/30/2014 |
|
09/01/2019 07/30/2022 |
50 | 09/01/2019 05/31/2024 |
0 -22 |
Begin Construction Phase
End Construction Phase |
01/15/2015 07/15/2017 |
|
09/06/2022 12/30/2024 |
0 | 06/01/2024 06/30/2027 |
-21 -30 |
Begin Closeout Phase
End Closeout Phase |
|
|
08/30/2025 |
0 | 07/01/2027 12/31/2027 |
0 -28 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.