Bridge No. 56C0084 - JACKSON STREET & WHITEWATER RIVER |
Description: Bridge No. 56C0084 - JACKSON STREET & WHITEWATER RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside County |
City | Indio |
Zip Code | 92201 |
Senate District |
28 |
Assembly District | 56 |
Congressional District | 36 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Indio | Vianka Orrantia | 760-391-4018 | vorrantia@indio.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$150 | $217 | $367 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,220 | $1,692 | $2,912 | ||||
Local** |
$8 | $2 | $10 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,378 | $1,911 | $3,289 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$70 | $15 | $85 | $83 | $83 | $2 | |
Right of Way |
$20 | $-20 | $0 | $0 | $0 | $0 | |
Construction |
$1,288 | $1,915 | $3,204 | $2,782 | $2,782 | $422 | |
Total* | $1,378 | $1,911 | $3,289 | $2,865 | $2,865 | $424 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
03/18/1997 |
|
03/18/1997 |
100 | 03/18/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/30/1999 03/30/2009 |
10/15/2009 |
01/30/1999 05/01/2010 |
100 | 08/23/2007 05/30/2011 |
-104 -13 |
Begin Right of Way Phase
End Right of Way Phase |
04/30/2009 08/30/2009 |
10/15/2009 |
04/30/2009 06/01/2010 |
100 | 08/30/2011 11/07/2018 |
-28 -103 |
Begin Construction Phase
End Construction Phase |
01/30/2010 04/30/2010 |
10/15/2009 10/15/2009 |
06/01/2010 09/30/2010 |
100 | 05/17/2019 03/05/2021 |
-109 -127 |
Begin Closeout Phase
End Closeout Phase |
10/30/2010 |
|
10/30/2010 |
100 | 08/02/2021 01/28/2022 |
-131 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$150,068 |
Current Approved: |
$367,470 |
Actual Expenditures: |
$319,093 |
Status as of December 31, 2023.