Bridge No. 56C0291 - JACKSON STREET & INDIO BOULEVARD |
Description: Bridge No. 56C0291 - JACKSON STREET & INDIO BOULEVARD - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside County |
City | Indio |
Zip Code | 92201 |
Senate District |
40 |
Assembly District | 56 |
Congressional District | 36 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Indio | Tom Rafferty | 760-391-4017 | trafferty@indio.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$298 | $-59 | $239 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,437 | $-459 | $1,978 | ||||
Local** |
$38 | $0 | $38 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $2,774 | $-519 | $2,255 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$153 | $0 | $153 | $155 | $155 | $-2 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$2,621 | $-519 | $2,102 | $2,206 | $2,206 | $-104 | |
Total* | $2,774 | $-519 | $2,255 | $2,362 | $2,362 | $-107 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
03/08/1997 |
|
03/08/1997 |
100 | 03/08/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/30/1999 03/30/2009 |
10/15/2009 |
01/30/1999 05/01/2010 |
100 | 01/30/1999 01/31/2011 |
0 -9 |
Begin Right of Way Phase
End Right of Way Phase |
04/30/2009 08/30/2009 |
|
04/30/2009 08/30/2009 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/30/2010 08/30/2010 |
10/15/2009 10/15/2009 |
06/01/2010 09/30/2010 |
100 | 08/10/2011 03/25/2013 |
-14 -30 |
Begin Closeout Phase
End Closeout Phase |
04/30/2011 |
|
04/30/2011 |
50 | 01/07/2014 02/03/2014 |
-33 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$298,220 |
Current Approved: |
$238,732 |
Actual Expenditures: |
$237,795 |
Status as of December 31, 2023.