Caltrans Logo

Bridge No. 56C0291 - JACKSON STREET & INDIO BOULEVARD

Description: Bridge No. 56C0291 - JACKSON STREET & INDIO BOULEVARD - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside County
City Indio
Zip Code 92201
 
Senate District
40
Assembly District 56
Congressional District 36
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Indio Tom Rafferty 760-391-4017   trafferty@indio.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$298 $-59 $239
Non-bond Funding
State/Federal*
$2,437 $-459 $1,978
Local**
$38 $0 $38
Private***
$0 $0 $0
 
Total**** $2,774 $-519 $2,255

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$153 $0 $153 $155 $155 $-2
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,621 $-519 $2,102 $2,206 $2,206 $-104
 
Total* $2,774 $-519 $2,255 $2,362 $2,362 $-107

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

03/08/1997 
 

 
 

03/08/1997 
100   

03/08/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/30/1999 

03/30/2009 
 

10/15/2009 
01/30/1999 

05/01/2010 
100  01/30/1999 

01/31/2011 


-9 
Begin Right of Way Phase

End Right of Way Phase
04/30/2009 

08/30/2009 
 

 
04/30/2009 

08/30/2009 
100   

 


Begin Construction Phase

End Construction Phase
01/30/2010 

08/30/2010 
10/15/2009 

10/15/2009 
06/01/2010 

09/30/2010 
100  08/10/2011 

03/25/2013 
-14 

-30 
Begin Closeout Phase

End Closeout Phase
04/30/2011 

 
 

 
04/30/2011 

 
50  01/07/2014 

02/03/2014 
-33 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$298,220
Current Approved:
$238,732
Actual Expenditures:
$237,795

 

Status as of December 31, 2023.