Bridge No. 56C0292 - N/B INDIO BLVD. & WHITEWATER RIVER

Description: Bridge No. 56C0292 - N/B INDIO BLVD. & WHITEWATER RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside County
City Indio
Zip Code 92201
 
Senate District
18
Assembly District 36
Congressional District 25
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Indio Vianka Orrantia 760-391-4017   vorrantia@indio.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$120 $295 $415
Non-bond Funding
State/Federal*
$990 $3,132 $4,122
Local**
$15 $94 $109
Private***
$0 $0 $0
 
Total**** $1,124 $3,521 $4,646

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$70 $256 $326 $210 $210 $116
Right of Way
$20 $230 $250 $332 $332 $-82
Construction
$1,035 $3,035 $4,070 $4,086 $4,086 $-16
 
Total* $1,124 $3,521 $4,646 $4,628 $4,628 $17

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
 

03/18/1997 
 

 
 

03/18/1997 
100   

03/18/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/30/1999 

03/30/2009 
 

 
01/30/1999 

03/27/2018 
100  01/30/1999 

04/03/2017 


12 
Begin Right of Way Phase

End Right of Way Phase
04/30/2009 

08/30/2009 
 

 
09/10/2018 

11/06/2019 
100  09/10/2018 

11/06/2019 


Begin Construction Phase

End Construction Phase
01/30/2010 

06/30/2010 
 

 
11/01/2020 

12/30/2022 
100  01/20/2021 

01/23/2023 
-3 

-1 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

03/30/2023 
50  02/01/2023 

06/30/2024 


-15 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$120,206
Current Approved:
$414,870
Actual Expenditures:
$414,870

 

Status as of December 31, 2023.