Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 56C0292 - N/B INDIO BLVD. & WHITEWATER RIVER |
Description: Bridge No. 56C0292 - N/B INDIO BLVD. & WHITEWATER RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside County |
City | Indio |
Zip Code | 92201 |
Senate District |
18 |
Assembly District | 36 |
Congressional District | 25 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Indio | Vianka Orrantia | 760-391-4017 | vorrantia@indio.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$120 | $295 | $415 | ||||
Non-bond Funding | |||||||
State/Federal* |
$990 | $3,132 | $4,122 | ||||
Local** |
$15 | $94 | $109 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $1,124 | $3,521 | $4,646 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$70 | $256 | $326 | $210 | $210 | $116 | |
Right of Way |
$20 | $230 | $250 | $332 | $332 | $-82 | |
Construction |
$1,035 | $3,035 | $4,070 | $4,086 | $4,086 | $-16 | |
Total* | $1,124 | $3,521 | $4,646 | $4,628 | $4,628 | $17 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
03/18/1997 |
|
03/18/1997 |
100 | 03/18/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/30/1999 03/30/2009 |
|
01/30/1999 03/27/2018 |
100 | 01/30/1999 04/03/2017 |
0 12 |
Begin Right of Way Phase
End Right of Way Phase |
04/30/2009 08/30/2009 |
|
09/10/2018 11/06/2019 |
100 | 09/10/2018 11/06/2019 |
0 0 |
Begin Construction Phase
End Construction Phase |
01/30/2010 06/30/2010 |
|
11/01/2020 12/30/2022 |
100 | 01/20/2021 01/23/2023 |
-3 -1 |
Begin Closeout Phase
End Closeout Phase |
|
|
03/30/2023 |
50 | 02/01/2023 06/30/2024 |
0 -15 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$120,206 |
Current Approved: |
$414,870 |
Actual Expenditures: |
$414,870 |
Status as of December 31, 2023.