Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 57C0010 - DOUGLAS DR & SAN LUIS REY RIVER |
Description: Bridge No. 57C0010 - DOUGLAS DR & SAN LUIS REY RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Diego County |
City | Oceanside |
Zip Code | 92054 |
Senate District |
38 |
Assembly District | 73 |
Congressional District | 49 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Oceanside | Kymberly Corbin | (760) 435-3534 | KCorbin@oceansideca.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$743 | $576 | $1,319 | ||||
Non-bond Funding | |||||||
State/Federal* |
$5,735 | $7,810 | $13,545 | ||||
Local** |
$500 | $-64 | $436 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $6,978 | $8,322 | $15,300 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$500 | $3,300 | $3,800 | $1,444 | $932 | $2,868 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$6,478 | $5,022 | $11,500 | $0 | $5,570 | $5,930 | |
Total* | $6,978 | $8,322 | $15,300 | $1,444 | $6,502 | $8,798 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/01/2006 12/31/2008 |
|
01/01/2006 12/31/2008 |
100 | 01/01/2006 12/31/2020 |
0 -146 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2007 06/30/2010 |
|
04/01/2021 02/28/2023 |
55 | 01/01/2021 06/04/2025 |
3 -28 |
Begin Right of Way Phase
End Right of Way Phase |
09/30/2009 06/30/2010 |
|
10/31/2022 12/31/2022 |
100 | 08/01/2021 01/25/2023 |
15 -1 |
Begin Construction Phase
End Construction Phase |
08/30/2010 12/30/2011 |
|
10/31/2023 10/31/2024 |
0 | 06/04/2025 12/15/2026 |
-19 -26 |
Begin Closeout Phase
End Closeout Phase |
|
|
04/30/2026 |
0 | 12/21/2026 06/30/2027 |
0 -14 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.