Bridge No. 57C0010 - DOUGLAS DR & SAN LUIS REY RIVER

Description: Bridge No. 57C0010 - DOUGLAS DR & SAN LUIS REY RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Diego County
City Oceanside
Zip Code 92054
 
Senate District
38
Assembly District 73
Congressional District 49
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Oceanside Kymberly Corbin (760) 435-3534   KCorbin@oceansideca.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$743 $576 $1,319
Non-bond Funding
State/Federal*
$5,735 $7,810 $13,545
Local**
$500 $-64 $436
Private***
$0 $0 $0
 
Total**** $6,978 $8,322 $15,300

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$500 $3,300 $3,800 $1,444 $932 $2,868
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$6,478 $5,022 $11,500 $0 $5,570 $5,930
 
Total* $6,978 $8,322 $15,300 $1,444 $6,502 $8,798

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/01/2006 

12/31/2008 
 

 
01/01/2006 

12/31/2008 
100  01/01/2006 

12/31/2020 


-146 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2007 

06/30/2010 
 

 
04/01/2021 

02/28/2023 
55  01/01/2021 

06/04/2025 


-28 
Begin Right of Way Phase

End Right of Way Phase
09/30/2009 

06/30/2010 
 

 
10/31/2022 

12/31/2022 
100  08/01/2021 

01/25/2023 
15 

-1 
Begin Construction Phase

End Construction Phase
08/30/2010 

12/30/2011 
 

 
10/31/2023 

10/31/2024 
06/04/2025 

12/15/2026 
-19 

-26 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

04/30/2026 
12/21/2026 

06/30/2027 


-14 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.