Bridge No. 57C0015 - NORTH HARBOR DR & NAVY ESTUARY

Description: Bridge No. 57C0015 - NORTH HARBOR DR & NAVY ESTUARY - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Diego County
City San Diego
Zip Code 92101
 
Senate District
39
Assembly District 76
Congressional District 53
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
San Diego Marnell Gibson (619)533-5213   MGibson@sandiego.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$1,901 $0 $1,901
Non-bond Funding
State/Federal*
$16,474 $0 $16,474
Local**
$47 $564 $611
Private***
$0 $0 $0
 
Total**** $18,422 $564 $18,987

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$1,848 $564 $2,412 $2,412 $2,412 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$16,574 $0 $16,574 $13,134 $13,145 $3,430
 
Total* $18,422 $564 $18,987 $15,546 $15,557 $3,430

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
04/30/1997 

09/30/1997 
 

 
04/30/1997 

09/30/1997 
100  04/30/1997 

09/30/1997 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/30/1997 

07/30/2007 
 

 
10/30/1997 

07/30/2007 
100  10/30/1997 

07/30/2007 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/30/2007 

06/30/2009 
10/15/2009 

10/15/2009 
08/30/2008 

09/15/2009 
100  08/30/2008 

09/15/2009 


Begin Closeout Phase

End Closeout Phase
12/30/2009 

 
 

 
12/30/2009 

 
50  12/30/2009 

06/15/2015 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N Y

Bond Funding Cost
Adopted:
$1,901,081
Current Approved:
$1,901,081
Actual Expenditures:
$1,351,438

 

Status as of December 31, 2023.