Bridge No. 57C0015 - NORTH HARBOR DR & NAVY ESTUARY |
Description: Bridge No. 57C0015 - NORTH HARBOR DR & NAVY ESTUARY - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Diego County |
City | San Diego |
Zip Code | 92101 |
Senate District |
39 |
Assembly District | 76 |
Congressional District | 53 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
San Diego | Marnell Gibson | (619)533-5213 | MGibson@sandiego.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$1,901 | $0 | $1,901 | ||||
Non-bond Funding | |||||||
State/Federal* |
$16,474 | $0 | $16,474 | ||||
Local** |
$47 | $564 | $611 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $18,422 | $564 | $18,987 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$1,848 | $564 | $2,412 | $2,412 | $2,412 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$16,574 | $0 | $16,574 | $13,134 | $13,145 | $3,430 | |
Total* | $18,422 | $564 | $18,987 | $15,546 | $15,557 | $3,430 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
04/30/1997 09/30/1997 |
|
04/30/1997 09/30/1997 |
100 | 04/30/1997 09/30/1997 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/30/1997 07/30/2007 |
|
10/30/1997 07/30/2007 |
100 | 10/30/1997 07/30/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/30/2007 06/30/2009 |
10/15/2009 10/15/2009 |
08/30/2008 09/15/2009 |
100 | 08/30/2008 09/15/2009 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
12/30/2009 |
|
12/30/2009 |
50 | 12/30/2009 06/15/2015 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$1,901,081 |
Current Approved: |
$1,901,081 |
Actual Expenditures: |
$1,351,438 |
Status as of December 31, 2023.