Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 57C0207 - N TORREY PINES RD & MTDB, BNSF RY, & AMTRAK |
Description: Bridge No. 57C0207 - N TORREY PINES RD & MTDB, BNSF RY, & AMTRAK - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego County |
City | Del Mar, San Diego |
Zip Code | 92014 |
Senate District |
39 |
Assembly District | 74, 75 |
Congressional District | 50, 53 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Del Mar | Joe Bride | (858) 755-3294 | jbride@delmar.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$3,426 | $-690 | $2,736 | ||||
Non-bond Funding | |||||||
State/Federal* |
$30,094 | $-4,810 | $25,283 | ||||
Local** |
$812 | $0 | $812 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $34,332 | $-5,501 | $28,831 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$4,460 | $465 | $4,925 | $4,896 | $4,896 | $28 | |
Right of Way |
$60 | $-7 | $53 | $0 | $0 | $53 | |
Construction |
$29,812 | $-5,959 | $23,853 | $22,397 | $22,397 | $1,457 | |
Total* | $34,332 | $-5,501 | $28,831 | $27,293 | $27,293 | $1,538 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
05/30/2007 09/30/2007 |
|
05/30/2007 09/30/2007 |
100 | 05/30/2007 09/30/2007 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/30/2002 10/30/2009 |
|
09/30/2002 10/30/2009 |
100 | 09/30/2002 03/12/2010 |
0 -4 |
Begin Right of Way Phase
End Right of Way Phase |
04/30/2008 10/30/2009 |
|
04/30/2008 10/30/2009 |
100 | 11/01/2008 10/30/2009 |
-6 0 |
Begin Construction Phase
End Construction Phase |
03/30/2010 09/30/2012 |
10/15/2009 10/08/2013 |
01/01/2010 07/31/2015 |
100 | 03/30/2010 08/11/2015 |
-3 0 |
Begin Closeout Phase
End Closeout Phase |
09/30/2013 |
|
09/30/2013 |
100 | 04/01/2014 05/19/2020 |
-6 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | Y | Y |
Bond Funding Cost | |
---|---|
Adopted: |
$3,426,318 |
Current Approved: |
$2,735,993 |
Actual Expenditures: |
$2,489,954 |
Status as of December 31, 2023.