Caltrans Logo

Bridge No. 57C0207 - N TORREY PINES RD & MTDB, BNSF RY, & AMTRAK

Description: Bridge No. 57C0207 - N TORREY PINES RD & MTDB, BNSF RY, & AMTRAK - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego County
City Del Mar, San Diego
Zip Code 92014
 
Senate District
39
Assembly District 74, 75
Congressional District 50, 53
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  Y    Y  
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Del Mar Joe Bride (858) 755-3294   jbride@delmar.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$3,426 $-690 $2,736
Non-bond Funding
State/Federal*
$30,094 $-4,810 $25,283
Local**
$812 $0 $812
Private***
$0 $0 $0
 
Total**** $34,332 $-5,501 $28,831

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$4,460 $465 $4,925 $4,896 $4,896 $28
Right of Way
$60 $-7 $53 $0 $0 $53
Construction
$29,812 $-5,959 $23,853 $22,397 $22,397 $1,457
 
Total* $34,332 $-5,501 $28,831 $27,293 $27,293 $1,538

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
05/30/2007 

09/30/2007 
 

 
05/30/2007 

09/30/2007 
100  05/30/2007 

09/30/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/30/2002 

10/30/2009 
 

 
09/30/2002 

10/30/2009 
100  09/30/2002 

03/12/2010 


-4 
Begin Right of Way Phase

End Right of Way Phase
04/30/2008 

10/30/2009 
 

 
04/30/2008 

10/30/2009 
100  11/01/2008 

10/30/2009 
-6 

Begin Construction Phase

End Construction Phase
03/30/2010 

09/30/2012 
10/15/2009 

10/08/2013 
01/01/2010 

07/31/2015 
100  03/30/2010 

08/11/2015 
-3 

Begin Closeout Phase

End Closeout Phase
09/30/2013 

 
 

 
09/30/2013 

 
100  04/01/2014 

05/19/2020 
-6 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted Y Y

Bond Funding Cost
Adopted:
$3,426,318
Current Approved:
$2,735,993
Actual Expenditures:
$2,489,954

 

Status as of December 31, 2023.