Bridge No. 57C0322 - HILL ST & SAN LUIS REY RIVER

Description: Bridge No. 57C0322 - HILL ST & SAN LUIS REY RIVER - Bridge Seismic Retrofit

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Diego County
City Oceanside
Zip Code 92054
 
Senate District
38
Assembly District 73
Congressional District 49
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Bridge Seismically Retrofitted  N      
 
Project Contacts Agency Contact Person Telephone E-mail
Seismic
Oceanside Luis Cardenas (760) 435-3573   LCardenas@oceansideca.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
LBSRA
$931 $-36 $895
Non-bond Funding
State/Federal*
$7,185 $35,026 $42,211
Local**
$200 $3,694 $3,894
Private***
$0 $0 $0
 
Total**** $8,316 $38,684 $47,000

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Preliminary Engineering
$200 $5,050 $5,250 $2,560 $5,394 $-144
Right of Way
$0 $5,000 $5,000 $0 $0 $5,000
Construction
$8,116 $28,634 $36,750 $0 $15,600 $21,150
 
Total* $8,316 $38,684 $47,000 $2,560 $20,994 $26,006

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Strategy Phase

End Strategy Phase
01/01/2008 

12/31/2008 
 

 
01/01/2008 

12/31/2008 
100  01/01/2008 

09/09/2021 


-154 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

06/30/2011 
 

12/22/2021 
05/26/2016 

07/31/2025 
48  01/01/2009 

07/31/2025 
90 

Begin Right of Way Phase

End Right of Way Phase
09/30/2010 

06/30/2011 
12/22/2021 

12/22/2021 
08/31/2023 

07/31/2025 
08/31/2023 

07/31/2025 


Begin Construction Phase

End Construction Phase
08/30/2011 

01/30/2012 
12/22/2021 

12/22/2021 
10/31/2025 

07/30/2027 
10/31/2025 

07/30/2027 


Begin Closeout Phase

End Closeout Phase
06/30/2013 

 
12/22/2021 

 
12/31/2028 

 
07/31/2027 

01/31/2028 
17 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Bridge Seismically Retrofitted N

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.