Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bridge No. 57C0322 - HILL ST & SAN LUIS REY RIVER |
Description: Bridge No. 57C0322 - HILL ST & SAN LUIS REY RIVER - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Diego County |
City | Oceanside |
Zip Code | 92054 |
Senate District |
38 |
Assembly District | 73 |
Congressional District | 49 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
Oceanside | Luis Cardenas | (760) 435-3573 | LCardenas@oceansideca.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$931 | $-36 | $895 | ||||
Non-bond Funding | |||||||
State/Federal* |
$7,185 | $35,026 | $42,211 | ||||
Local** |
$200 | $3,694 | $3,894 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $8,316 | $38,684 | $47,000 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$200 | $5,050 | $5,250 | $2,560 | $5,394 | $-144 | |
Right of Way |
$0 | $5,000 | $5,000 | $0 | $0 | $5,000 | |
Construction |
$8,116 | $28,634 | $36,750 | $0 | $15,600 | $21,150 | |
Total* | $8,316 | $38,684 | $47,000 | $2,560 | $20,994 | $26,006 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
01/01/2008 12/31/2008 |
|
01/01/2008 12/31/2008 |
100 | 01/01/2008 09/09/2021 |
0 -154 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 06/30/2011 |
12/22/2021 |
05/26/2016 07/31/2025 |
48 | 01/01/2009 07/31/2025 |
90 0 |
Begin Right of Way Phase
End Right of Way Phase |
09/30/2010 06/30/2011 |
12/22/2021 12/22/2021 |
08/31/2023 07/31/2025 |
0 | 08/31/2023 07/31/2025 |
0 0 |
Begin Construction Phase
End Construction Phase |
08/30/2011 01/30/2012 |
12/22/2021 12/22/2021 |
10/31/2025 07/30/2027 |
0 | 10/31/2025 07/30/2027 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/30/2013 |
12/22/2021 |
12/31/2028 |
0 | 07/31/2027 01/31/2028 |
17 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.