Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
I-10 and Riverside Avenue Interchange Reconstruction |
Description: Improve Interchange
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Rialto |
Zip Code | |
Senate District |
32 |
Assembly District | 62 |
Congressional District | 43 |
Caltrans District |
08 |
County/State Route | San Bernardino 10 |
Postmile Begin/End | 18.7 20.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Rialto | Abunnasr Husain | (909) 884-8276 | ahusain@sanbag.ca.gov | |
Design (PS&E) Phase |
City of Rialto | Abunnasr Husain | (909) 884-8276 | ahusain@sanbag.ca.gov | |
Right of Way Phase |
City of Rialto | Abunnasr Husain | (909) 884-8276 | ahusain@sanbag.ca.gov | |
Construction Phase |
City of Rialto | Abunnasr Husain | (909) 884-8276 | ahusain@sanbag.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$14,096 | $-4,259 | $9,837 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,452 | $0 | $1,452 | ||||
Local** |
$18,452 | $0 | $18,452 | ||||
Total**** | $34,000 | $-4,259 | $29,741 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$1,885 | $0 | $1,885 | $0 | $0 | $1,885 | |
Right of Way |
$2,470 | $0 | $2,470 | $0 | $0 | $2,470 | |
Construction |
$29,645 | $-4,259 | $25,386 | $0 | $0 | $25,386 | |
Total* | $34,000 | $-4,259 | $29,741 | $0 | $0 | $29,741 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/1997 03/31/2008 |
|
06/01/1997 03/31/2008 |
100 | 09/17/1997 05/31/1999 |
-3 108 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/03/2001 09/30/2008 |
|
04/03/2001 09/30/2008 |
100 | 06/18/2002 03/31/2010 |
-15 -18 |
Begin Right of Way Phase
End Right of Way Phase |
04/01/2008 09/30/2008 |
|
04/01/2008 09/30/2008 |
100 | 06/18/2002 06/24/2009 |
70 -9 |
Begin Construction Phase
End Construction Phase |
06/01/2009 09/30/2010 |
08/13/2009 08/13/2009 |
01/01/2010 01/01/2012 |
100 | 02/11/2010 02/29/2012 |
-1 -2 |
Begin Closeout Phase
End Closeout Phase |
10/01/2010 12/01/2010 |
|
10/01/2010 12/01/2010 |
100 | 06/22/2012 03/03/2015 |
-21 -52 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$14,096,000 |
Current Approved: |
$9,837,000 |
Actual Expenditures: |
$9,837,000 |
Status as of December 31, 2023.