Caltrans Logo

I-10 and Riverside Avenue Interchange Reconstruction

Description: Improve Interchange

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Rialto
Zip Code
 
Senate District
32
Assembly District 62
Congressional District 43
 
Caltrans District
08
 
 
County/State Route San Bernardino 10
Postmile Begin/End 18.7 20.8
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Rialto Abunnasr Husain (909) 884-8276   ahusain@sanbag.ca.gov
Design (PS&E) Phase
City of Rialto Abunnasr Husain (909) 884-8276   ahusain@sanbag.ca.gov
Right of Way Phase
City of Rialto Abunnasr Husain (909) 884-8276   ahusain@sanbag.ca.gov
Construction Phase
City of Rialto Abunnasr Husain (909) 884-8276   ahusain@sanbag.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$14,096 $-4,259 $9,837
Non-bond Funding
State/Federal*
$1,452 $0 $1,452
Local**
$18,452 $0 $18,452
 
Total**** $34,000 $-4,259 $29,741

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$1,885 $0 $1,885 $0 $0 $1,885
Right of Way
$2,470 $0 $2,470 $0 $0 $2,470
Construction
$29,645 $-4,259 $25,386 $0 $0 $25,386
 
Total* $34,000 $-4,259 $29,741 $0 $0 $29,741

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/1997 

03/31/2008 
 

 
06/01/1997 

03/31/2008 
100  09/17/1997 

05/31/1999 
-3 

108 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/03/2001 

09/30/2008 
 

 
04/03/2001 

09/30/2008 
100  06/18/2002 

03/31/2010 
-15 

-18 
Begin Right of Way Phase

End Right of Way Phase
04/01/2008 

09/30/2008 
 

 
04/01/2008 

09/30/2008 
100  06/18/2002 

06/24/2009 
70 

-9 
Begin Construction Phase

End Construction Phase
06/01/2009 

09/30/2010 
08/13/2009 

08/13/2009 
01/01/2010 

01/01/2012 
100  02/11/2010 

02/29/2012 
-1 

-2 
Begin Closeout Phase

End Closeout Phase
10/01/2010 

12/01/2010 
 

 
10/01/2010 

12/01/2010 
100  06/22/2012 

03/03/2015 
-21 

-52 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) 1 1

Bond Funding Cost
Adopted:
$14,096,000
Current Approved:
$9,837,000
Actual Expenditures:
$9,837,000

 

Status as of December 31, 2023.