Bridge No. 57C0416 - FIRST AVE & MAPLE CANYON |
Description: Bridge No. 57C0416 - FIRST AVE & MAPLE CANYON - Bridge Seismic Retrofit
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego County |
City | San Diego |
Zip Code | 92103 |
Senate District |
39 |
Assembly District | 76 |
Congressional District | 53 |
Caltrans District |
11 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
Seismic |
San Diego | Kevin Perez | 619-533-3063 | kperez@sandiego.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LBSRA |
$698 | $0 | $698 | ||||
Non-bond Funding | |||||||
State/Federal* |
$6,288 | $0 | $6,288 | ||||
Local** |
$640 | $0 | $640 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $7,626 | $0 | $7,626 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Preliminary Engineering |
$1,540 | $0 | $1,540 | $1,473 | $1,473 | $67 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$6,086 | $0 | $6,086 | $6,009 | $6,009 | $77 | |
Total* | $7,626 | $0 | $7,626 | $7,482 | $7,482 | $144 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Strategy Phase
End Strategy Phase |
11/30/2003 06/30/2004 |
|
11/30/2003 06/30/2004 |
100 | 11/30/2003 06/30/2004 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/30/2004 10/30/2007 |
|
06/09/1993 06/06/2008 |
100 | 06/09/1993 06/06/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/30/2008 09/30/2009 |
|
11/17/2008 03/22/2010 |
100 | 11/17/2008 03/22/2010 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/30/2010 |
|
01/30/2010 05/30/2011 |
50 | 01/30/2010 05/30/2011 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bridge Seismically Retrofitted | N |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.